The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost?   Activity Immediate predecessor Normal time Expedited time Normal cost ($) Expedited cost ($)   1 - 4 3 5,000 6,900   2 - 2 2 3,000 3,000   3 1 5 4 7,000 9,200   4 2 6 4 9,000 11,000   5 2 5 4 6,000 7,800   6 3, 4 3 2 4,000 6,500   7 4, 5 5 4 8,000 11,000     ANSWERS: (a) Critical path(s): ________________, Expected duration of the project_______, Total project cost ________ b) How could the project time be reduced to 11 weeks and what is the total project cost?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
  1. The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost?

 

Activity

Immediate predecessor

Normal time

Expedited time

Normal cost ($)

Expedited cost ($)

 

1

-

4

3

5,000

6,900

 

2

-

2

2

3,000

3,000

 

3

1

5

4

7,000

9,200

 

4

2

6

4

9,000

11,000

 

5

2

5

4

6,000

7,800

 

6

3, 4

3

2

4,000

6,500

 

7

4, 5

5

4

8,000

11,000

 

 

ANSWERS:

(a) Critical path(s): ________________, Expected duration of the project_______, Total project cost ________

  1. b) How could the project time be reduced to 11 weeks and what is the total project cost?

___________________________________________________________________________________________________________________________________________________________________________________

Expert Solution
Step 1

A project network diagram is a graphic depiction of a project's process. A network diagram is a chart containing boxes indicating tasks and responsibilities, as well as arrows indicating the timetable and order in which the work must be accomplished.

The term critical path can be understood as the longest path that can be taken in order to accomplish the entire project. This helps in decision-making by identifying the critical path that requires the most resources.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.