The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost? Activity Immediate predecessor Normal time Expedited time Normal cost ($) Expedited cost ($) 1 - 4 3 5,000 6,900 2 - 2 2 3,000 3,000 3 1 5 4 7,000 9,200 4 2 6 4 9,000 11,000 5 2 5 4 6,000 7,800 6 3, 4 3 2 4,000 6,500 7 4, 5 5 4 8,000 11,000 ANSWERS: (a) Critical path(s): ________________, Expected duration of the project_______, Total project cost ________ b) How could the project time be reduced to 11 weeks and what is the total project cost?
- The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost?
|
Activity |
Immediate predecessor |
Normal time |
Expedited time |
Normal cost ($) |
Expedited cost ($) |
|
1 |
- |
4 |
3 |
5,000 |
6,900 |
|
2 |
- |
2 |
2 |
3,000 |
3,000 |
|
3 |
1 |
5 |
4 |
7,000 |
9,200 |
|
4 |
2 |
6 |
4 |
9,000 |
11,000 |
|
5 |
2 |
5 |
4 |
6,000 |
7,800 |
|
6 |
3, 4 |
3 |
2 |
4,000 |
6,500 |
|
7 |
4, 5 |
5 |
4 |
8,000 |
11,000 |
ANSWERS:
(a) Critical path(s): ________________, Expected duration of the project_______, Total project cost ________
- b) How could the project time be reduced to 11 weeks and what is the total project cost?
___________________________________________________________________________________________________________________________________________________________________________________
A project network diagram is a graphic depiction of a project's process. A network diagram is a chart containing boxes indicating tasks and responsibilities, as well as arrows indicating the timetable and order in which the work must be accomplished.
The term critical path can be understood as the longest path that can be taken in order to accomplish the entire project. This helps in decision-making by identifying the critical path that requires the most resources.