The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job ▼ A E B C D ▼ E C B D A ▼ A B C E D ▼ A B D C E ▼ C B D E A
The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job ▼ A E B C D ▼ E C B D A ▼ A B C E D ▼ A B D C E ▼ C B D E A
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
Related questions
Question
The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day
23)
at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival.
Job
|
Time Since
Order Arrived
(days ago)
|
Processing
Time (days)
|
Due Date
(days from
now)
|
A
|
11
|
10
|
22
|
B
|
10
|
8
|
13
|
C
|
8
|
4
|
19
|
D
|
6
|
4
|
16
|
E
|
1
|
3
|
30
|
a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due.
Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:
Sequence
|
1
|
2
|
3
|
4
|
5
|
Job
|
▼
A
E
B
C
D
|
▼
E
C
B
D
A
|
▼
A
B
C
E
D
|
▼
A
B
D
C
E
|
▼
C
B
D
E
A
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,