The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent to final assembly for an important customer order. Currently, all eight jobs are in department X and must be routed to department Y after processing. The processing times (in days) for each job in each department follow: Dept/Job Dept. X Dept. Y A B D E F G H 2 2 5 4 7 5 4 10 3 6 3 8 6 6 Develop two schedules for operations in both departments. For your first schedule, use the SPT priority rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display your schedules (i.e. a timeline).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
3)
to final assembly for an important customer order. Currently, all eight jobs are in department X and
must be routed to department Y after processing. The processing times (in days) for each job in each
department follow:
The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent
Dept/Job
Dept. X
Dept. Y
A
B
C
D
E
F
G
H
2
4
7
5
4
10
3
3
8
2
6
5
Develop two schedules for operations in both departments. For your first schedule, use the SPT priority
rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two
schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display
your schedules (i.e. a timeline).
Transcribed Image Text:3) to final assembly for an important customer order. Currently, all eight jobs are in department X and must be routed to department Y after processing. The processing times (in days) for each job in each department follow: The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent Dept/Job Dept. X Dept. Y A B C D E F G H 2 4 7 5 4 10 3 3 8 2 6 5 Develop two schedules for operations in both departments. For your first schedule, use the SPT priority rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display your schedules (i.e. a timeline).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.