The length of time taken to complete a particular task on a construction site is found to be Normally distributed with mean 45 min and standard deviation 10 min. Calculate the probability that the task will take between 30 min and an hour. Give your answer to three decimal places. Answer:

A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
icon
Related questions
Question
The length of time taken to complete a particular task on a construction
site is found to be Normally distributed with mean 45 min and standard
deviation 10 min. Calculate the probability that the task will take between
30 min and an hour.
Give your answer to three decimal places.
Answer:
Transcribed Image Text:The length of time taken to complete a particular task on a construction site is found to be Normally distributed with mean 45 min and standard deviation 10 min. Calculate the probability that the task will take between 30 min and an hour. Give your answer to three decimal places. Answer:
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
A First Course in Probability (10th Edition)
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability
A First Course in Probability
Probability
ISBN:
9780321794772
Author:
Sheldon Ross
Publisher:
PEARSON