The labour unit cost of excavation by hand referring to the crew calculations is:
O $134.27/m3
O $142.82/m3
O $106.97/m3
O None of the above
QUESTION 6
The labour unit cost of excavation by hand referring to the man-hour calculations is:
$134.67/m3
O $156.25/m3
$106.76/m3
O None of the above
QUESTION 7
The man hour productivity rate for hand trimming is:
O 0.52 mh/m2
O 1.13 mh/m2
1.19 mh/m2
None of the above
Transcribed Image Text:The labour unit cost of excavation by hand referring to the crew calculations is: O $134.27/m3 O $142.82/m3 O $106.97/m3 O None of the above QUESTION 6 The labour unit cost of excavation by hand referring to the man-hour calculations is: $134.67/m3 O $156.25/m3 $106.76/m3 O None of the above QUESTION 7 The man hour productivity rate for hand trimming is: O 0.52 mh/m2 O 1.13 mh/m2 1.19 mh/m2 None of the above
Trade
Cost
Production
Productivity
Hourly Cost
Unit Cost
Number
Hourly
Activity
Unit
of
Crew
Man hours
Name
workers in
Rates
Duration Output Man hours Crew Hours
Man hour
Crew
Cost
Cost
Crew
($)
(hour)
(unit)
(mh/unit)
(ch/unit)
($/ch)
($/mh)
($/unit)
(S/unit)
2
3
4
5
6
7
8
10
11
12
13
EXCAVATION
A. Excavate by hand
m3
EL
5
$36.00
20.00
36.00
EF
1.5
$41.00
B. Hand Trimming
m2
EL
4
$38.00
5.00
20.00
EF
0.75
$42.00
CONCRETE
C. Cast in Place Concrete
m
CL
$39.00
12.00
94.00
CF
$44.00
m2
$42.00
10.00
60.00
D. Formwork Footings
Activate Wind
Go to Settings to ac
DELL
home
end
prt sc
F10
F1
F9
F8
F7
F6
F5
F4
Transcribed Image Text:Trade Cost Production Productivity Hourly Cost Unit Cost Number Hourly Activity Unit of Crew Man hours Name workers in Rates Duration Output Man hours Crew Hours Man hour Crew Cost Cost Crew ($) (hour) (unit) (mh/unit) (ch/unit) ($/ch) ($/mh) ($/unit) (S/unit) 2 3 4 5 6 7 8 10 11 12 13 EXCAVATION A. Excavate by hand m3 EL 5 $36.00 20.00 36.00 EF 1.5 $41.00 B. Hand Trimming m2 EL 4 $38.00 5.00 20.00 EF 0.75 $42.00 CONCRETE C. Cast in Place Concrete m CL $39.00 12.00 94.00 CF $44.00 m2 $42.00 10.00 60.00 D. Formwork Footings Activate Wind Go to Settings to ac DELL home end prt sc F10 F1 F9 F8 F7 F6 F5 F4
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning