The Hickory Company manufactures wooden desks. Management schedules overtime every weekend to reduce the backlog on the most popular models. The automatic routing machine is used to cut certain types of edges on the desktops. The following orders need to be scheduled for the routing machine: Order Time Since Order Arrived (hours ago) Estimated Machine Time (hours) Due Date (hours from now) 1 1 9 20 2 0 7 21 3 6 8 12 4 5 5 3 3 12 8 18 The due dates reflect the need for the order to be at its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours. Using the FCFS (first come, first served) decision rule for sequencing the orders, the order is: Sequence Order 1 2 3 4 5 3 4 5 1 2 Using the EDD (earliest due date) decision rule for sequencing the orders, the order is (to resolve a tie, use order in which the orders were received): Sequence Order 1 2 3 4 5 4 3 5 1 2 The average flow time and average past due hours for each option are (enter your responses are real numbers rounded to two decimal places): Rule EDD Average Flow Time Average Past Due Hours FCFS 21.6 23 7 10.4

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
help please answer in text form with proper workings and explanation for each and every part and steps with concept and introduction no AI no copy paste remember answer must be in proper format with all working
The Hickory Company manufactures wooden desks. Management schedules overtime every weekend to reduce the backlog on the most popular models. The automatic routing machine is used to
cut certain types of edges on the desktops. The following orders need to be scheduled for the routing machine:
Order
Time Since Order
Arrived (hours ago)
Estimated Machine
Time (hours)
Due Date
(hours from now)
1
1
9
20
2
0
7
21
3
6
8
12
4
5
5
3
3
12
8
18
The due dates reflect the need for the order to be at its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and
average past due hours.
Using the FCFS (first come, first served) decision rule for sequencing the orders, the order is:
Sequence
Order
1
2
3
4
5
3
4
5
1
2
Using the EDD (earliest due date) decision rule for sequencing the orders, the order is (to resolve a tie, use order in which the orders were received):
Sequence
Order
1
2
3
4
5
4
3
5
1
2
The average flow time and average past due hours for each option are (enter your responses are real numbers rounded to two decimal places):
Rule
EDD
Average Flow Time Average Past Due Hours
FCFS
21.6
23
7
10.4
Transcribed Image Text:The Hickory Company manufactures wooden desks. Management schedules overtime every weekend to reduce the backlog on the most popular models. The automatic routing machine is used to cut certain types of edges on the desktops. The following orders need to be scheduled for the routing machine: Order Time Since Order Arrived (hours ago) Estimated Machine Time (hours) Due Date (hours from now) 1 1 9 20 2 0 7 21 3 6 8 12 4 5 5 3 3 12 8 18 The due dates reflect the need for the order to be at its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours. Using the FCFS (first come, first served) decision rule for sequencing the orders, the order is: Sequence Order 1 2 3 4 5 3 4 5 1 2 Using the EDD (earliest due date) decision rule for sequencing the orders, the order is (to resolve a tie, use order in which the orders were received): Sequence Order 1 2 3 4 5 4 3 5 1 2 The average flow time and average past due hours for each option are (enter your responses are real numbers rounded to two decimal places): Rule EDD Average Flow Time Average Past Due Hours FCFS 21.6 23 7 10.4
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.