The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS a A 1 4 B 5 2 5 11 D A 1 9 B 3 C,D D,E F 6. 11 G 1 2 3 H F,G 3 3 b. What is the critical path? O A-D-G-H O A-D-F-H O B-E-G-H O A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) Probability

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
The following represents a project that should be scheduled using CPM:
TIMES (DAYS)
IMMEDIATE
PREDECESSORS
АСTIVITY
a
m
A
1
4
7
B.
5
A
2
5
11
A
1
8
9
B
1
3
C,D
D,E
F,G
1 6
1 2
11
G
3
H
2
3
3
b. What is the critical path?
O A-D-G-H
O A-D-F-H
O B-E-G-H
O A-C-F-H
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
roject completion time
days
d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct
probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final
answer to 4 decimal places.)
Probability
Transcribed Image Text:The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE PREDECESSORS АСTIVITY a m A 1 4 7 B. 5 A 2 5 11 A 1 8 9 B 1 3 C,D D,E F,G 1 6 1 2 11 G 3 H 2 3 3 b. What is the critical path? O A-D-G-H O A-D-F-H O B-E-G-H O A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) roject completion time days d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) Probability
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.