The following CPM network has estimates of the normal time in weeks listed for the activities: (в(2) (D(5) (F(4) (A(7) (G(5) C(4) (E(2) a. Identify the critical path. O A-C-D-F-G O A-B-D-F-G O A-C-D-E-G O A-B-D-E-G b. What is the length of time to complete the project? Number of weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
The following CPM network has estimates of the normal time in weeks listed for the activities:
B(2)
D(5)
(F(4)
(A(7)
(G(5)
C(4)
(E(2)
a. Identify the critical path.
O A-C-D-F-G
O A-B-D-F-G
O A-C-D-E-G
O A-B-D-E-G
b. What is the length of time to complete the project?
Number of weeks
Transcribed Image Text:The following CPM network has estimates of the normal time in weeks listed for the activities: B(2) D(5) (F(4) (A(7) (G(5) C(4) (E(2) a. Identify the critical path. O A-C-D-F-G O A-B-D-F-G O A-C-D-E-G O A-B-D-E-G b. What is the length of time to complete the project? Number of weeks
c. Which activities have slack, and how much?
OC, 2 weeks; F, 3 weeks.
O B, 2 weeks; E, 2 weeks.
OC, 1 week; E, 2 weeks.
O D, 1 week; E, 2 weeks.
Here is a table of normal and crash times and costs.
NORMAL
CRASH
NORMAL
CRASH
ACTIVITY
ΤΙΜE
TIME
COST
COST
$ 8,000
$7,000
5,000
9,000
3,000
2,000
A
6
B
7,000
10, 200
4,500
3,000
7,000
3
D
4
E
F
4
2
4, 000
5,000
G
4
8,000
d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
O B, D
O B, C
O A, E
O A, C
d-2. What would be the total incremental cost?
Total incremental cost
7244n245
Transcribed Image Text:c. Which activities have slack, and how much? OC, 2 weeks; F, 3 weeks. O B, 2 weeks; E, 2 weeks. OC, 1 week; E, 2 weeks. O D, 1 week; E, 2 weeks. Here is a table of normal and crash times and costs. NORMAL CRASH NORMAL CRASH ACTIVITY ΤΙΜE TIME COST COST $ 8,000 $7,000 5,000 9,000 3,000 2,000 A 6 B 7,000 10, 200 4,500 3,000 7,000 3 D 4 E F 4 2 4, 000 5,000 G 4 8,000 d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? O B, D O B, C O A, E O A, C d-2. What would be the total incremental cost? Total incremental cost 7244n245
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.