The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Item S Gross req Order release Week 1 2 3 4 5 6 7 Lead Time (weeks) 2 Level The product structure. 0 T(1) 1 S U(1) 2 V (2) W (1) X (1) Y (2) Z (3) ☑ The time-phased product structure. Y N V W T ☑ S ✓ U 1 2 3 4 5 6 7 Time in weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of
X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2
weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z.
Click the icon to view the product structure and the time-phased product structure.
In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units
are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Item
S
Gross req
Order release
Week
1
2
3
4 5
6
7
Lead Time
(weeks)
2
Transcribed Image Text:The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Item S Gross req Order release Week 1 2 3 4 5 6 7 Lead Time (weeks) 2
Level
The product structure.
0
T(1)
1
S
U(1)
2 V (2) W (1) X (1) Y (2) Z (3)
☑
The time-phased product structure.
Y
N
V
W
T
☑
S
✓
U
1
2 3 4 5
6
7
Time in weeks
Transcribed Image Text:Level The product structure. 0 T(1) 1 S U(1) 2 V (2) W (1) X (1) Y (2) Z (3) ☑ The time-phased product structure. Y N V W T ☑ S ✓ U 1 2 3 4 5 6 7 Time in weeks
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.