The demand for subassembly S is 140 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Construct a gross material requirements plan (type 0 if the input box is not used). Item S Gross req Order release T Gross req Order release U Gross req Order release V Gross req Order release W Gross req Order release 1 2 3 Week 4 5 6 7 Lead Time (weeks) 2 2 2 3 x Gross req Order release 2 Y Gross req Order release 2 Z Gross req 1 Order release More Info Level The product structure. The time-phased product structure. 0 T(1) 1 S U(1) 2 V(1) W(2) X(2) Y(2) Z(3) V W T X S Y U Z 2 3 Time in weeks -co 6 7

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
please fill this out
The demand for subassembly S is 140 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2
weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Construct a gross material requirements plan (type 0 if the input box is not used).
Item
S
Gross req
Order release
T
Gross req
Order release
U
Gross req
Order release
V
Gross req
Order release
W
Gross req
Order release
1
2
3
Week
4
5
6
7
Lead Time
(weeks)
2
2
2
3
x
Gross req
Order release
2
Y
Gross req
Order release
2
Z
Gross req
1
Order release
Transcribed Image Text:The demand for subassembly S is 140 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Construct a gross material requirements plan (type 0 if the input box is not used). Item S Gross req Order release T Gross req Order release U Gross req Order release V Gross req Order release W Gross req Order release 1 2 3 Week 4 5 6 7 Lead Time (weeks) 2 2 2 3 x Gross req Order release 2 Y Gross req Order release 2 Z Gross req 1 Order release
More Info
Level
The product structure.
The time-phased product structure.
0
T(1)
1
S
U(1)
2 V(1) W(2) X(2) Y(2) Z(3)
V
W
T
X
S
Y
U
Z
2
3
Time in weeks
-co
6
7
Transcribed Image Text:More Info Level The product structure. The time-phased product structure. 0 T(1) 1 S U(1) 2 V(1) W(2) X(2) Y(2) Z(3) V W T X S Y U Z 2 3 Time in weeks -co 6 7
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.