The Blair Company's three assembly plants are located in California, Georgia, and New Jersey. Previously, the company purchased a major subassembly, which becomes part of the final product, from an outside firm. Blair has decided to manufacture the subassemblies within the company and must now consider whether to rent one centrally located facility (e.g., in Missouri, where all the subassemblies would be manufactured) or to rent three separate facilities, each located near one of the assembly plants, where each facility would manufacture only the subassemblies needed for the nearby assembly plant. A single, centrally located facility, with a production capacity of 18,000 units per year, would have fixed costs of $900,000 per year and a variable cost of $250 per unit. Three separate decentralized facilities, with production capacities of 8,000, 6,000, and 4,000 units per year, would have fixed costs of $475,000, $425,000, and $400,000, respectively, and variable costs per unit of only $225 per unit, owing primarily to the reduction in shipping costs. The current production rates at the three assembly plants are 6,000, 4,500, and 3,000 units, respectively. Assuming that the current production rates are maintained at the three assembly plants, which alternative should management select? Three separate decentralized facilities O Single, centrally located facility If demand for the final product were to increase to production capacity, which alternative would be more attractive? O Single, centrally located facility O Three separate decentralized facilities

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
6. Exercise 8.6
The Blair Company's three assembly plants are located in California, Georgia, and New Jersey. Previously, the company purchased a major
subassembly, which becomes part of the final product, from an outside firm. Blair has decided to manufacture the subassemblies within the company
and must now consider whether to rent one centrally located facility (e.g., in Missouri, where all the subassemblies would be manufactured) or to rent
three separate facilities, each located near one of the assembly plants, where each facility would manufacture only the subassemblies needed for the
nearby assembly plant. A single, centrally located facility, with a production capacity of 18,000 units per year, would have fixed costs of $900,000 per
year and a variable cost of $250 per unit. Three separate decentralized facilities, with production capacities of 8,000, 6,000, and 4,000 units per year,
would have fixed costs of $475,000, $425,000, and $400,000, respectively, and variable costs per unit of only $225 per unit, owing primarily to the
reduction in shipping costs. The current production rates at the three assembly plants are 6,000, 4,500, and 3,000 units, respectively.
Assuming that the current production rates are maintained at the three assembly plants, which alternative should management select?
O Three separate decentralized facilities
Single, centrally located facility
If demand for the final product were to increase to production capacity, which alternative would be more attractive?
O Single, centrally located facility
Three separate decentralized facilities
Transcribed Image Text:6. Exercise 8.6 The Blair Company's three assembly plants are located in California, Georgia, and New Jersey. Previously, the company purchased a major subassembly, which becomes part of the final product, from an outside firm. Blair has decided to manufacture the subassemblies within the company and must now consider whether to rent one centrally located facility (e.g., in Missouri, where all the subassemblies would be manufactured) or to rent three separate facilities, each located near one of the assembly plants, where each facility would manufacture only the subassemblies needed for the nearby assembly plant. A single, centrally located facility, with a production capacity of 18,000 units per year, would have fixed costs of $900,000 per year and a variable cost of $250 per unit. Three separate decentralized facilities, with production capacities of 8,000, 6,000, and 4,000 units per year, would have fixed costs of $475,000, $425,000, and $400,000, respectively, and variable costs per unit of only $225 per unit, owing primarily to the reduction in shipping costs. The current production rates at the three assembly plants are 6,000, 4,500, and 3,000 units, respectively. Assuming that the current production rates are maintained at the three assembly plants, which alternative should management select? O Three separate decentralized facilities Single, centrally located facility If demand for the final product were to increase to production capacity, which alternative would be more attractive? O Single, centrally located facility Three separate decentralized facilities
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Multiple Equilibria
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education