Teloxy Engineering (A) Teloxy Engineering has received a onetime contract to design and build 10 000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. Some members felt that it would be more economical to purchase the product for R200 each in the marketplace, with an extra R20 per unit handling of the 10 000 units. The Management team set up a meeting with the manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. The manufacturing team informs them that it can produce a maximum of 10,000 units, just enough to fulfil the contract. The setup cost will be R100 000 and the raw material cost is R120 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects:

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Teloxy Engineering (A)
Teloxy Engineering has received a onetime contract to design and build 10 000 units of a new product. During the proposal
process, management felt that the new product could be designed and manufactured at a low cost. Some members felt
that it would be more economical to purchase the product for R200 each in the marketplace, with an extra R20 per unit
handling of the 10 000 units.
The Management team set up a meeting with the manufacturing team to see if they can manufacture the component at a
cheaper price than buying it from the outside. The manufacturing team informs them that it can produce a maximum of
10,000 units, just enough to fulfil the contract. The setup cost will be R100 000 and the raw material cost is R120 per
component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects:
% defective
10
20
30
40
Probability of occurrence (%)
10
20
30
25
15
All defective units must be removed and repaired at a cost of R60 per unit.
Adapted from: Kezner, H. R. (2017). Project Management Case Studies. New Jersey: John Wiley & Sons, Inc.
Question 1
1.1. If there is a 20% probability of defective product occurrence during production, determine if it is economically better to
make or buy the unit? *Show all your calculations.
1.2. Teloxy Engineering wants to determine if it should invest in setting up a manufacturing plant worth R12 000 000 or
invest in project Theta worth R12 000 000 by applying the payback analysis. The table below shows the initial
investment cost of the two projects and their expected revenues. Calculate the payback period of the investments.
Determine the outcome If Teloxy management requires a 5 year or less recovery period for the initial investment.
Transcribed Image Text:Teloxy Engineering (A) Teloxy Engineering has received a onetime contract to design and build 10 000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. Some members felt that it would be more economical to purchase the product for R200 each in the marketplace, with an extra R20 per unit handling of the 10 000 units. The Management team set up a meeting with the manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. The manufacturing team informs them that it can produce a maximum of 10,000 units, just enough to fulfil the contract. The setup cost will be R100 000 and the raw material cost is R120 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects: % defective 10 20 30 40 Probability of occurrence (%) 10 20 30 25 15 All defective units must be removed and repaired at a cost of R60 per unit. Adapted from: Kezner, H. R. (2017). Project Management Case Studies. New Jersey: John Wiley & Sons, Inc. Question 1 1.1. If there is a 20% probability of defective product occurrence during production, determine if it is economically better to make or buy the unit? *Show all your calculations. 1.2. Teloxy Engineering wants to determine if it should invest in setting up a manufacturing plant worth R12 000 000 or invest in project Theta worth R12 000 000 by applying the payback analysis. The table below shows the initial investment cost of the two projects and their expected revenues. Calculate the payback period of the investments. Determine the outcome If Teloxy management requires a 5 year or less recovery period for the initial investment.
PROJECT (Manufacturing Plant)
PROJECT (Theta)
Year
Outlays
Revenues
Outlays
Revenues
12 000 000
12 000 000
1
1 200 000
2 000 000
2
3 400 000
1 270 000
3
5 400 000
6 000 000
4
7 000 000
5 550 000
5
9 050 000
8 000 000
Transcribed Image Text:PROJECT (Manufacturing Plant) PROJECT (Theta) Year Outlays Revenues Outlays Revenues 12 000 000 12 000 000 1 1 200 000 2 000 000 2 3 400 000 1 270 000 3 5 400 000 6 000 000 4 7 000 000 5 550 000 5 9 050 000 8 000 000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.