Suad​ Alwan, the purchasing agent for Dubai​ Airlines, has determined that the third plane took 20,000 hours to produce. Using an 80​% learning curve and a $40​-per-hour labor​ charge, he wants to determine the cost of the four additional planes.   a) Time required for the fourth unit = 18,231 hours b) Cost of the fourth unit = ? dollars (round to the nearest whole number)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Suad​ Alwan, the purchasing agent for Dubai​ Airlines, has determined that the third plane took 20,000 hours to produce. Using an 80​% learning curve and a $40​-per-hour labor​ charge, he wants to determine the cost of the four additional planes.  

a) Time required for the fourth unit = 18,231 hours

b) Cost of the fourth unit = ? dollars (round to the nearest whole number)

Expert Solution
Given details:

Find the Given details below:

Given details:
Time taken for Third plane (Hour) 20000
Learning curve 80%
Labor charge (Per Hour)  $                                         40

 

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

c) Time required for the sixth unit = ?

d) Cost of the sixth unit = ?

 

Solution
Bartleby Expert
SEE SOLUTION
Follow-up Question

d) Cost of the fifth unit = ?  (round your response to the nearaest whole number.

(How do I find the calculation for this question?)

Solution
Bartleby Expert
SEE SOLUTION
Follow-up Question

c)Time required for the fifth unit​ = ? enter your response here hours​ (round your response to the nearest whole​ number).

Solution
Bartleby Expert
SEE SOLUTION
Follow-up Question

c) Time required for the fifth unit​ = ? hours​ (round your response to the nearest whole​ number).

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.