A new robotic toy which needs to be produced at a rate of 200 units/day. (Assume 8 hours/day) Using the largest candidate rule method, develop a balanced work station to meet the production goal and determine the efficiency of the configuration. Task Time(in minutes) Immediate Predecessors 1 12 --- 2 6 --- 3 2 1 4 5 2,3 5 4 4 6 4 4 7 7 5
A new robotic toy which needs to be produced at a rate of 200 units/day. (Assume 8 hours/day) Using the largest candidate rule method, develop a balanced work station to meet the production goal and determine the efficiency of the configuration.
Task Time(in minutes) Immediate Predecessors
1 12 ---
2 6 ---
3 2 1
4 5 2,3
5 4 4
6 4 4
7 7 5