Spin Cycle Architecture uses three activity pools to apply overhead to its projects. Each activity has a cost driver used to allocate the overhead costs to the projects. The activities and related overhead costs are as follows: initial concept formation $40,000, design $300,000, and construction oversight $100,000. The cost drivers and expected use are as follows. Expected Use of Cost Drivers Activities Cost Drivers per Activity Initial concept formation Number of project changes 20 Design Squarefeet 150,000 Construction oversight Number of months 100 (a) Compute the predetermined overhead rate for each activity. (b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Spin Cycle Architecture uses three activity pools to apply
Expected Use of Cost Drivers Activities Cost Drivers per Activity
Initial concept formation Number of project changes 20 Design Squarefeet 150,000 Construction oversight Number of months 100
(a) Compute the predetermined overhead rate for each activity. (b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.