Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. In 2018, it incurs cost of $5,325,000. At December 31, 2019, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18,000,000 due to unanticipated price increases. What is the cost that Seasons has incurred during the year ended December 31, 2019?
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. In 2018, it incurs cost of $5,325,000. At December 31, 2019, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18,000,000 due to unanticipated price increases. What is the cost that Seasons has incurred during the year ended December 31, 2019?
Group of answer choices
$7,875,000
$8,175,000
$7,987,500
$13,500,000
Trending now
This is a popular solution!
Step by step
Solved in 2 steps