Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Day Job #151 was scheduled to begin on day 3 and to take 6 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time. Job #179 was scheduled to start on day 7 and take 2 days. It actually got started on day 6 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. Job 12 34 56789 10 11 151 177 This exercise contains only part a. 179 a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the dashed line provided for each of the tasks. 211 215 Now

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end
of day 7, Ron is reviewing the Gantt chart depicting these schedules:
Day
Job #151 was scheduled to begin on day 3 and to take 6 days. It got started on time and is 1 day ahead of schedule.
Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time.
Job #179 was scheduled to start on day 7 and take 2 days. It actually got started on day 6 and is progressing according
to plan.
Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected
and should take 3 days.
Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days.
Job 12 3 4 56 789 10 11
--
151
177 +
This exercise contains only part a.
179
a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already
plotted). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of
(overlapping) the dashed line provided for each of the tasks.
211
215
Now
Transcribed Image Text:Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Day Job #151 was scheduled to begin on day 3 and to take 6 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time. Job #179 was scheduled to start on day 7 and take 2 days. It actually got started on day 6 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. Job 12 3 4 56 789 10 11 -- 151 177 + This exercise contains only part a. 179 a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted). Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the dashed line provided for each of the tasks. 211 215 Now
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.