Questions #1, #2, and #3 are about the following situation. You have been given the information in the MRP table below. Part: PR28 Gross Requirements (GR) Scheduled Receipts (SR) Projected On-Hand Inventory (POH) Planned Order Recipes (Porec) Planned Order Releases (PORel) |Q=10; LT=2; SS = 15 10 units in Week #4 20 units in Week #3 O 10 units Week #2 0 20 units in Week #1 25 1 10 Which of the following is a correct planned order release (PORel) for the table? 2 12 30 Week # 3 16 4 0 5 18
Questions #1, #2, and #3 are about the following situation. You have been given the information in the MRP table below. Part: PR28 Gross Requirements (GR) Scheduled Receipts (SR) Projected On-Hand Inventory (POH) Planned Order Recipes (Porec) Planned Order Releases (PORel) |Q=10; LT=2; SS = 15 10 units in Week #4 20 units in Week #3 O 10 units Week #2 0 20 units in Week #1 25 1 10 Which of the following is a correct planned order release (PORel) for the table? 2 12 30 Week # 3 16 4 0 5 18
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
Related questions
Question
Answer both clearly
![Questions #1, #2, and #3 are about the following situation.
You have been given the information in the MRP table below.
Part: PR28
Gross Requirements (GR)
Scheduled Receipts (SR)
Projected On-Hand
Inventory (POH)
Planned Order Recipes
(Porec)
Planned Order Releases
(PORel)
Q = 10; LT = 2; SS = 15
10 units in Week #4
20 units in Week #3
10 units Week #2
0
20 units in Week #1
25
1
10
2
12
Which of the following is a correct planned order release (PORel) for the table?
30
Week #
3
16
4
0
5
18](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F9564feaa-6fb0-462d-b11c-c6502e5617a7%2F283a163a-d3dc-4156-b3cc-8824b89d655a%2Fgyxbhco_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Questions #1, #2, and #3 are about the following situation.
You have been given the information in the MRP table below.
Part: PR28
Gross Requirements (GR)
Scheduled Receipts (SR)
Projected On-Hand
Inventory (POH)
Planned Order Recipes
(Porec)
Planned Order Releases
(PORel)
Q = 10; LT = 2; SS = 15
10 units in Week #4
20 units in Week #3
10 units Week #2
0
20 units in Week #1
25
1
10
2
12
Which of the following is a correct planned order release (PORel) for the table?
30
Week #
3
16
4
0
5
18
![This question is about the MRP table in Question #1.
What is projected on-hand inventory (POH) in Week #2?
O 19 units
15 units
17 units
33 units](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F9564feaa-6fb0-462d-b11c-c6502e5617a7%2F283a163a-d3dc-4156-b3cc-8824b89d655a%2Fbvtniw8_processed.jpeg&w=3840&q=75)
Transcribed Image Text:This question is about the MRP table in Question #1.
What is projected on-hand inventory (POH) in Week #2?
O 19 units
15 units
17 units
33 units
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,