Question 4 You are currently working on a project to be completed in 20 months. The budget of the project is R12 000 000. Six months have passed, and the schedule says that 30% of the work should be completed. To date R2 800 000 has been spent already, however on a closer review; you find that only 15% of work has been completed. 4.1. Calculate the project's Planned Value (PV). 4.2. Calculate the project's Earned Value (EV). 4.3. Calculate the project's Cost Variance (CV) and determine if the project is under budget or over budget. 4.4. Calculate the project's Schedule Variance (SV) and determine if the project is behind schedule or ahead of schedule.
Question 4 You are currently working on a project to be completed in 20 months. The budget of the project is R12 000 000. Six months have passed, and the schedule says that 30% of the work should be completed. To date R2 800 000 has been spent already, however on a closer review; you find that only 15% of work has been completed. 4.1. Calculate the project's Planned Value (PV). 4.2. Calculate the project's Earned Value (EV). 4.3. Calculate the project's Cost Variance (CV) and determine if the project is under budget or over budget. 4.4. Calculate the project's Schedule Variance (SV) and determine if the project is behind schedule or ahead of schedule.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Question 4
You are currently working on a project to be completed in 20 months. The budget of the project is R12 000 000. Six
months have passed, and the schedule says that 30% of the work should be completed. To date R2 800 000 has been
spent already, however on a closer review; you find that only 15% of work has been completed.
4.1. Calculate the project's Planned Value (PV).
4.2. Calculate the project's Earned Value (EV).
4.3. Calculate the project's Cost Variance (CV) and determine if the project is under budget or over budget.
4.4. Calculate the project's Schedule Variance (SV) and determine if the project is behind schedule or ahead of schedule.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.