Question 25 Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time(a), the most likely completion time(m), and the pessimistic completion time (b) (all in days) for a new contract are given in the following table: Activity m b Immediate Predecessor(s) a A B с D E F G H 1 J 2 4 K 2 6 1 2 5 11 5 8 5 6 14 3 79 G 16 18 C 5 9 13 H, I Activities on the critical path for the project are 4 7 8 C 3 5 B, D 3 4 A, E 13 A, E 12 13 F 9 CDEGIK, 38 days OCDEGHIK, 46 days CDEGIK, 42 days BDEGIK, 32 days and the project duration is around 1 pts days.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 25
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to
complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time(a), the
most likely completion time(m), and the pessimistic completion time (b) (all in days) for a new contract are given in the following table:
Activity am b Immediate Predecessor(s)
A
2
4
MONEY
B
C
D
F
G
1
J
2
K
C
B, D
A, E
13. A, E
12 13 F
7
9 G
14
16
18 C
5 9 13 H, I
Activities on the critical path for the project are
6
1
5
5
11
3
7
3
3
9
8
6
CDEGIK, 38 days
CDEGHIK, 46 days
CDEGIK, 42 days
BDEGIK, 32 days
4
8
5
4
and the project duration is around
1 pts
days.
Transcribed Image Text:Question 25 Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time(a), the most likely completion time(m), and the pessimistic completion time (b) (all in days) for a new contract are given in the following table: Activity am b Immediate Predecessor(s) A 2 4 MONEY B C D F G 1 J 2 K C B, D A, E 13. A, E 12 13 F 7 9 G 14 16 18 C 5 9 13 H, I Activities on the critical path for the project are 6 1 5 5 11 3 7 3 3 9 8 6 CDEGIK, 38 days CDEGHIK, 46 days CDEGIK, 42 days BDEGIK, 32 days 4 8 5 4 and the project duration is around 1 pts days.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.