F Question Viewer 16 E F 20 Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places): Activity Expected Time A 0 B с D 23 ☐☐☐☐☐
Question content area
Part 1
A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed:
Activity |
a |
|
m |
|
b |
|
A |
10 |
|
16 |
|
19 |
|
B |
26 |
|
31 |
|
41 |
|
C |
18 |
|
18 |
|
18 |
|
D |
8 |
|
14 |
|
20 |
|
E |
17 |
|
18 |
|
20 |
|
F |
16 |
|
20 |
|
23 |
|
Part 2
Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places):
|
|
|
|
|
|
Part 3
|
|
|
Part 4
|
|
|
Part 5
|
|
|
Part 6
|
|
|
Part 7
|
|
|
Part 8
Based on the activity time estimates, standard deviation for each of the activities is (enter your responses rounded to two decimal places):