Questión 2 Refer to Appendix A for tables and equations to be used. Use the CNCI method. You are given the following design parameters for a concrete mix: The compressive strength of the concrete mix must be 40 MPa after 28 days. The cement that is going to be used is a CEM I 52.5 with a relative density of 3.14. The stone available is a 19.0 mm stone with a dry compacted bulk density (CBD) of 1780 kg/m³ and a relative

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
1.
Question 2
Refer to Appendix A for tables and equations to be used. Use the CNCI method.
You are given the following design parameters for a concrete mix:
The compressive strength of the concrete mix must be 40 MPa after 28 days. The cement
that is going to be used is a CEM I 52.5 with a relative density of 3.14. The stone available
is a 19.0 mm stone with a dry compacted bulk density (CBD) of 1780 kg/m³ and a relative
density of 2.24. An average, natural sand with a fineness modulus of 2.45 and a relative
density of 2.86 is going to be used for the mix. The slump on site is specified as 75 mm.
The concrete is going to be compacted by moderate vibration on site.
Calculate and show the amount of water, cement, stone and sand that is needed to make
up 1 m of concrete mix as specified above.
water requirementinliters
w:c ratio
• Cement content (kg/m3 of concrete) =
• Mst = CBDS: (K – 0.1 FM)
M.
M..
• Vols = 1000 –(
+
D.
Transcribed Image Text:1. Question 2 Refer to Appendix A for tables and equations to be used. Use the CNCI method. You are given the following design parameters for a concrete mix: The compressive strength of the concrete mix must be 40 MPa after 28 days. The cement that is going to be used is a CEM I 52.5 with a relative density of 3.14. The stone available is a 19.0 mm stone with a dry compacted bulk density (CBD) of 1780 kg/m³ and a relative density of 2.24. An average, natural sand with a fineness modulus of 2.45 and a relative density of 2.86 is going to be used for the mix. The slump on site is specified as 75 mm. The concrete is going to be compacted by moderate vibration on site. Calculate and show the amount of water, cement, stone and sand that is needed to make up 1 m of concrete mix as specified above. water requirementinliters w:c ratio • Cement content (kg/m3 of concrete) = • Mst = CBDS: (K – 0.1 FM) M. M.. • Vols = 1000 –( + D.
APPENDIX A
To be given in with the answering book
Name:
Student number:
APPENDIX B
Table 1: w:c ratios for certain cementitious materials:
Water:cement(w:c) ratio
Specified
strength of
mix(28 days.
MPa)
CEM I 32.5 MPa
CEM I 42.5 MPA
CEM I 52.5 MPa
0.72
0.82
99'0
0.61
25
0.67
0.77
0.62
0.57
0.56
0.72
0.53
0.5
35
0.67
0.52
0.62
Table 2: water requirement for a concrete mix where 19.0 mm aggregate is use
and a 75 mm slump is specified:
Water content I/m3
Sand quality
natural
crusher
Very poor
240
235
225
225
Jood
average
210
215
195
205
poob
excellent
180
195
Table 3: values of K for determining stone content:
Approxima
te slump
compaction
Maximum size of stone. mm
range. mm
9.5
13.2
19.0
26.5
37.5
Hand
75 - 150
0.75
0.84
0.94
1.05
compaction
Moderate
vibration
00'
25 - 100
0.80
0.80
1.06
1.10
00'L
0 - 25
Heavy vibration
00'L
1.05
1.10
1.15
Formula's for calculating the material requirements for a concrete mix design:
Transcribed Image Text:APPENDIX A To be given in with the answering book Name: Student number: APPENDIX B Table 1: w:c ratios for certain cementitious materials: Water:cement(w:c) ratio Specified strength of mix(28 days. MPa) CEM I 32.5 MPa CEM I 42.5 MPA CEM I 52.5 MPa 0.72 0.82 99'0 0.61 25 0.67 0.77 0.62 0.57 0.56 0.72 0.53 0.5 35 0.67 0.52 0.62 Table 2: water requirement for a concrete mix where 19.0 mm aggregate is use and a 75 mm slump is specified: Water content I/m3 Sand quality natural crusher Very poor 240 235 225 225 Jood average 210 215 195 205 poob excellent 180 195 Table 3: values of K for determining stone content: Approxima te slump compaction Maximum size of stone. mm range. mm 9.5 13.2 19.0 26.5 37.5 Hand 75 - 150 0.75 0.84 0.94 1.05 compaction Moderate vibration 00' 25 - 100 0.80 0.80 1.06 1.10 00'L 0 - 25 Heavy vibration 00'L 1.05 1.10 1.15 Formula's for calculating the material requirements for a concrete mix design:
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Types of Cement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning