QUESTION 2 A 7.2% upgrade meets a 1.4% upgrade. The operating speed for the road is 100 km/h. The chainage and reduced levels 80 m after the vertical curve are 1420.00m and 96.055m respectively. (a) Determine the vertical curve length to be adopted (round your answer to the nearest 50m). (b) Calculate the RL and chainage at TP1. (c) Calculate the RL on the gradeline and curve at chainage 1287.00m.
Q: True or false?A) When analyzing a retaining wall using Coulomb’s theory, the weight of the soil…
A: When analyzing a retaining wall using Coulomb’s theory, the weight of the soil above the wall is…
Q: HI, I AM AN ARCHITECTURE STUDENT, THIS IS MY STUDIO PROJECT AND IT HAS A CANTILEVER PART, I NEED…
A: Approach to solving the question: Answer the given question.
Q: pls calculate the problem in detail with explanation that's shown in the image. Will give an upvote…
A: First, we need to calculate the total load on the beam. The total load is the product of the load…
Q: Q2,Using the ACI "Direct Design Method" for the interior panel (A) in figure below: (a) Check by ACI…
A: Part (a): Check Slab ThicknessAccording to the ACI code, the minimum slab thickness for two-way…
Q: Answer should be 24.6mm, but the work to find it is not given. Could you help please, thank you!
A: Step 1: Step 2: Step 3: Step 4:
Q: I need detailed explanation solving this exercise from Foundation Engineering, step by step please.
A:
Q: A company has been hired to carry out an assessment on a reinforced concrete railway tunnel which…
A: Step 1:Step 2:Step 3:Step 4:
Q: hand writing please and take your timeand thanks for you
A: Detailed explanation:Step 1: Understanding the Earned Value (EV)Earned Value (EV) represents the…
Q: Question td A simply supported steel beam with dimensions L=2m, b=100mm, d=10mm is subjected to…
A: ExplanationGiven Data:Beam length, L=2mWidth of the beam, b=100mm=0.1mDepth (thickness) of the beam,…
Q: What Successful case leading the project by adequately coordinating construction equipment.
A: More explain
Q: I need detailed explanation solving this exercise from Foundation Engineering, step by step please.
A: 3. (A) Construction of Drilled Shafts Using the Casing Method:The casing method of drilled shaft…
Q: Note: Please provide a concise working out with a handwritten solution only, ensuring no AI…
A: Step 1:Step 2:Step 3:Step 4:
Q: The following figure shows a centrifugal pump that is used for pumping water fromone tank to another…
A: Detailed explanation:
Q: Assessment 3 Not answered Question 1 8 9 10 7 Answered 04:59 Question 8 out of 10 Name the types of…
A: To answer the question "Name the types of controls you can use to prevent falling objects from…
Q: Determine the reactions and calculate the force in each member of thetruss and state if the members…
A:
Q: The beam shown in the figure is subjected to a moment M and a concentrated force P. [P = 12 kips, M…
A: Step 1: Step 2: Step 3: Step 4:
Q: I need detailed help solving exercise 2 from Engineering Math. Step by step, please.
A: Step 1:Step 2:Step 3:
Q: Q1. Calculate the normal and the shear stress on the AB plane as shown in the following figure. 100…
A: The problem is asking us to calculate the normal and shear stress on a plane AB. The given…
Q: Thumbs-up will be given. Please write the complete solutions and Write Legibly. A 289mm x 324mm…
A: The given values are as follows:Cross-sectional dimensions of the column: 289mm x 324mmEffective…
Q: The answers that was given to me by you earlier were incorrect please help re solve
A:
Q: Part A A solar water heater mounted on the roof consists of two flat plates. Water enters at A and…
A:
Q: I don't want the solution to be from artificial intelligence. If the solution is sent from…
A:
Q: . Prepare and label two sketches, one with the vertical angle greater than 90 degrees, and one with…
A:
Q: What will be the filter thickness to increase the safety factor (left sheet pile) against boiling to…
A:
Q: Outside air at a temperature of 25° C is drawn into the duct and then heated along the duct at 149…
A:
Q: Use the attached diagram and draw it as an isometric. Determine the number of Ts, elbows, couples…
A: Elbows:Count each 90-degree corner in the diagram where an elbow fitting would be required.Based on…
Q: I need detailed explanation solving this exercise from Foundation Engineering, step by step please.
A:
Q: Which of the following is the first step in the planning and scheduling process?…
A: The planning and scheduling process in project management is a systematic approach to planning,…
Q: 3. Determine the approximate axial forces, shears, and moments for all the members of the frame…
A: Detailed Explanation: Problem Statement: Tasked with determining the approximate axial forces,…
Q: 20 mm weld 150 mm 50 mm 50 mm 20 mm
A:
Q: Performance data for a pump are listed in the following table.Hp (ft) 179 176 165 145 119 84 43Q…
A:
Q: Project management
A: Determining the logical steps to reduce the project duration using the time-cost trade-off process…
Q: Note: Please provide a clear, step-by-step handwritten working out (no explanations!), ensuring it…
A:
Q: 25. A single L6×6×1 is used as a tension brace in a multi-story building. One leg of the angle is…
A:
Q: What is the purpose of a horizontal curve?
A: In civil engineering, particularly in the design of roads and highways, a horizontal curve provides…
Q: 1- What are the design parameters in sprinkler irrigation system? 2- Define precipitation rate and…
A: Design Parameters in a Sprinkler Irrigation SystemThese are the key factors you consider when…
Q: An activated sludge process with an aeration basin of 4,000 m³ is treating a wastewater flow of…
A: Given Data- Aeration basin volume (V) = 4000 m³- Influent flow rate (Q) = 7500 m³/day- Influent BOD₅…
Q: I need detailed explanation solving this exercise from Foundation Engineering, step by step please.
A: Step 1: Step 2:Step 3: Step 4:
Q: 20 mm weld 150 mm 50 mm 50 mm 20 mm
A:
Q: Use the standard reduction potentials located in the 'Tables' linked above to calculate the…
A: Fe2+(aq) + Co(s) → Fe(s) + Co2+(aq) Standard reduction potentialsEo(Fe2+/Fe) = -0.44 VEo(Co2+/Co) =…
Q: A leaky confined aquifer is overlain with unconfined aquifer. The estimated recharge rate from the…
A: Approach to solving the question:The vertical hydraulic conductivity of the aquifer was determined…
Q: I need detailed explanation solving this exercise from Foundation Engineering, step by step please.
A: More example
Q: A short post, 150 mm by 150 mm, of Douglas fir, is reinforced by the addition of two ASTM A36 steel…
A: The cross-sectional area of the wood (Aw) can be calculated using the formula for the area of a…
Q: References for the Denton Creek Regional Wastewater plant?
A: Here are some references for the Denton Creek Regional Wastewater Plant:Trinity River Authority…
Q: Please show all work, including; Ma? Ay? V at A,B,C. Shear diagram, M/EI diagram, tB/C, tC/A…
A:
Q: ↑ E Tt Freeform © B > ☐ Boxed Include all FBD, show only calculation and final answers Not…
A: Step 1:Step 2:Step 3:Step 4:
Q: Would it be worth it to develop public transportation in a city with less than 1500 people?
A: Hope this helps
Q: I need detailed help solving this exercise from homework of Engineering Math. I do not really…
A:
Q: USING THE SLOPE DEFLECTION METHOD, DRAW THE SHEAR AND MOMENT DIAGRAM. PLS SHOW YOUR FULL SOLUTION.
A:
Q: The beam is subjected to a uniform dead load of 200 lb / ft and a single live load of 5 k.…
A: Step 1:Step 2:Step 3: Step 4:
Step by step
Solved in 2 steps with 3 images
- (b) For the safe road design and smooth traffic flow, combination of transition and circular curve will be constructed to combine two tangent line that have bearing of N 70° E (entry tangent) and S 80° E (exit tangent) respectively. With the aid of sketch, design the minimum length of transition curve and circular curve that has the following characteristics • Design speed = 110 km/hr coefficient of side friction, f= 0.15 Superelevation, e = 5 % • Radial acceleration, c = 0.9 m/s³For the following conditions: Design speed 60 mph, V/C ratio = 0.6, Level of service = Curve radius, 955 ft, Time value = $4/hr. If the basic section cost for passenger cars on a multilane highway is $206/KV-M, estimate the highway grade. B, %3DThe project speed is 100 km/h on a divided state road with a vertical curve. The driver's transition reaction time is 2.0 seconds; the friction coefficient is 0.4. Accordingly, calculate the following: a) The slopes of g, and g2. b) The vertical curve length (L). c) Calculate the grade line elevation of the points T1 and T2 as well every 30 meters and present them in a table format. Note: use the Stopping sight distance to solve thia
- PROBLEM #1) An existing highway with bearing of N 20deg E to be connected to another highway, with bearing of N 75deg E, by a 4-degree simple curve. What length of curve is required? (SIMPLE AND COMPOUND CURVES) *PLEASE REFER TO THE FORMULAS BELOW*Calculate the maximum permissible speed on curve of high speed B.G. track having the following particulars: Degree of the curve =2°, Amount of superelevation = 150 m, Max. speed of the section likely to be sanctioned = 165 kmph. = 8.0 cm, Length of transition curveQ1. A rising gradient AB and a falling gradient BC are to be connected by a vertical curve. Based on the data given in Table Q1, design the curve at 20 metres intervals. First Grade (± %) Second Grade (± %) Sighting Distance (SSD) Driver's eye (h₂) Object height (h₂) 3.6 -1.7 150 1.05 0.3 Table Q1 (Units are in metres) RL of highest/lowest pt Chainage of highest/lowest pt 38.788 3621.191
- A rising gradient AB and a falling gradient BC are to be connected by a vertical curve. Based on the data given in Table Q1, design the curve at 20 metres intervals. Table Q1 (Units are in metres) First Grade (± %) Second Grade (+ %) Sighting Distance (SSD) Driver's eye (h₁) Object height (h₂) 4.2 -1.8 145 1.05 0.3 F G RL of highest/lowest pt Chainage of highest/lowest pt| H 39.171 4048.600 KQ1) The project speed is 100 km/h on a divided state road with a vertical curve. The driver's transition reaction time is 2.0 seconds; the friction coefficient is 0.4. Accordingly, calculate the following: a) The slopes of and g2. b) The vertical curve length (L). c) Calculate the grade line elevation of the points T1 and T2 as well every 30 meters and present them in a table format. T1 A Station 0+000 Elevation = 400 m Station 1+200 Elevation 460 m P T2 B Station 2+200 Elevation 490 mThe arterial road with a 100 km/h design speed will be constructed on the flat terrain. At one section, the equal tangent vertical curve as shown in Table 3 is proposed. Table 3: Parameters of Vertical Alignment Length 490 m PVC station 3+700.000 PVC elevation 460 m Initial grade -3.5% Final grade 6.5% (a) Calculate the stationing and elevation of the low point, PVI and PVT. (b) Calculate the minimum length of curve to meet stopping sight distance requirements
- C. Design a Two way - one lane Highway with the following specification. V - 90 kph e - 0.05 m. 15 m SD - 115 m wheel base - 2.25 m c- 3 Pavement is rotated at center | - 20° Determine the following: Minimum Radius Road Widening Transition Spiral (if any) Vertical Curve Tangent and Length of Curve Road Profile for horizontal alignment with station if the start station is 1 • 000Question in PictureThere is a need for conducting a design check for a horizontal curve (flat terrain) for an intermediate speed highway in rural Victoria. Given the design speed is 80kmph and super elevation is 7%. The provided horizontal curve radius was equal to the 700 m. Would the designed curve radius will be sufficient to attain the super elevation? If not, what would be the correct radius for horizontal curve? When suggesting a new radius please check and make sure that the provide super elevation is higher (>7%) than required.