Chapter 14, Problem 17P
The following table shows the stations and ordinates for a mass diagram. The free-haul distance is 600 ft. Overhaul cost is $12 per station yard.
(a) Use the method of moments to compute the additional cost that must be paid to the contractor.
(b) Sketch the ground profile if the finished grade of this roadway section is level (0 percent).
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A-1.10% grade meets a +0.60% grade at station 36+00 and elevation 800.00 ft. The
+0.60 grade then joins a +2.40 grade at station 39+00.
Part A
Determine the elevation at the low point of the curve.
Express your answer in feet to six significant figures.
Elev =
Submit
Part B
VAΣo↓ vec
Request Answer
Determine the station at the low point of the curve.
Submit
O 38+42.763
O 35+40.763
O 36+42.763
O 36+44.763
Request Answer
?
ft
Determine the cross sectional area for a 10m wide roadway at Sta 12+198 using the given cross section notes:
Round your answer to 3 decimal places.
Show the illustration/diagram. Show complete and detailed solution.
From station 0 + 040 whose center height is 1.2 m. fill, the ground line has a uniform sclope of 6.5% going to station 0 + 100 with a center height of 3.5m. Solve for the grade of the finished roadway.
Chapter 14 Solutions
Traffic and Highway Engineering
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Q2- Find the required area of cut/fill (m2) and Calculate the net volumes (m3) between each two stations. The road width value 13 The total road length is 330 m. Filling shrinkage ratio is 15 % The road elevation at the C.L of station (0+00) is 10.00 m. with 4 % uphill gradient RL = Road level, GL = Ground level Station 6+00 Station 7+00 GL GL 1.5m 2.0m RL 2% 6:1 RL 2% 5:1arrow_forwardHelp asap thanks I'll ratearrow_forwardPlease answer the questions in the picture please, Show all of your work. Thank you.arrow_forward
- This is not an assignment question and not a graded question..... It's important to me..... Please solve urgent.... Thank youarrow_forwardDetermine the cross sectional area for a 9m wide roadway at Sta 12+198 using the given cross section notes in the image:arrow_forwardHomework Q1: A driver of a vehicle traveling at 90 kph up-grade requires 96m to sto after he applied the brakes, less than another driver traveling at the same speed down the ame grade, if the coefficient of longitudinal friction is 0.3. What is the percent grade of thatsection and what is the total stopping sight distance on the down grade? Q2: In the figure shown below, its required to calculate the minimum distane (D) for placing the right turn sign to enable a driver on the major road (A) to turn his vehicl into minor road (B)?arrow_forward
- O 1::0Y O Home Work No 2.. Home Work No. 2 A vehicle initially traveling at (75 mile/hr.), skids to a stop taking (170) m to do so. the coefficient of skidding resistance (0.36). What should the grade be for this roadway. (Use t = 2.5 sec.). II >arrow_forwardAnswer the given problem ASAParrow_forwardQ1- Find the required area of cut/fill (m2) and Calculate the net volumes(m3) hetween each two stations. The road width is 13 and the total road length is 330m filling shrinkage ratio 15% The road elevation at the C.L of station(0+00)is 10.00m.with 4% uphill gradient RL = Road level, GL = Ground level %3D !! Station 0+00 Station 1+00 (10.00 m) RL 2% 2% RL 4:1 6:1 0.9m 1.1m GL GLarrow_forward
- A reversed curve with diverging tangent is to be designed to connect to three traversed lines for the portion of the proposed highway. The lines AB is 185 m, BC is 122.40 m, and CD is 285 m. The azimuth are Due East, 242°, and 302° respectively. The following are the cost index and specification: Type of Pavement = Item 311 (Portland Cement Concrete Pavement) Number of Lanes = Two Lanes Width of Pavement = 3.05 m per lane Thickness of Pavement = 280 mm Unit Cost = P1,900 per square meter It is necessary that the PRC (Point of Reversed Curvature) must be one-fourth the distance BC from B. A) Find the radius of the first curve. B) Find the length of road from A to D. Use arc basis. C) Find the cost of the concrete pavement from A to D. ERSIarrow_forwardA reversed curve with diverging tangent is to be designed to connect to three traversed lines for the portion of the proposed highway. The lines AB is 185 m, BC is 122.40 m, and CD is 285 m. The azimuth are Due East, 242°, and 302° respectively. The following are the cost index and specification: Type of Pavement = Item 311 (Portland Cement Concrete Pavement) Number of Lanes = Two Lanes Width of Pavement = 3.05 m per lane Thickness of Pavement = 280 mm Unit Cost = P1,800 per square meter It is necessary that the PRC (Point of Reversed Curvature) must be one-fourth the distance BC from B. Find the radius of the first curve.arrow_forwardA reversed curve with diverging tangent is to be designed to connect to three traversed lines for the portion of the proposed highway. The lines AB is 185 m, BC is 122.40 m, and CD is 285 m. The azimuth are Due East, 242°, and 302° respectively. The following are the cost index and specification: Type of Pavement = Item 311 (Portland Cement Concrete Pavement) Number of Lanes = Two Lanes Width of Pavement = 3.05 m per lane Thickness of Pavement = 280 mm Unit Cost = P1,900 per square meter It is necessary that the PRC (Point of Reversed Curvature) must be one-fourth the distance BC from B. A) Find the radius of the first curve. B) Find the length of road from A to D. Use arc basis. C) Find the cost of the concrete pavement from A to D.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License