Question 13: A group of final year students would like to start up their business on the campus of the university they are currently studying. They have consulted several owners of on-going business on the campus and have obtained the following information: Activity Description A Prepare Company Profile Immediate Time Estimates Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) 1 4 7 4 B Prepare Proposal Paper CDE Obtain Business License MOF registration A,B A,B Register with Companies Commission Malaysia C,D F Audited Report E G Obtain Tax Payment License H Obtain Business Premises License D E,F,G 1 Briefing H J Interview H K Roundtable Discussion H L Acquire Tender I,J,K M Complete Agreement of renting & Stamping M 22226332HI 1 1 1 1 3544 7552233m 8 006627733 14 N Proceed With Business L 7 14 5452 21 QUESTIONS: (a) Draw the project network. (b) Apply PERT/CPM and provide the information or table on the ES, EF, LS, LF and slack times for all the activities. What are the critical activities? (c) What is the expected completion time for the project? What is the probability of completing the project within this duration? (d) What is the probability of completing this project within 49 days? (e) In order to be 90% confident in meeting the deadline, how long should they allocate to start establishing their business (f) Is it possible to delay Activity J without affecting the project's completion time? Why

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question
Question 13:
A group of final year students would like to start up their business on the campus of the
university they are currently studying. They have consulted several owners of on-going
business on the campus and have obtained the following information:
Activity
Description
A
Prepare Company Profile
Immediate
Time Estimates
Predecessor Optimistic (a) Most Likely (m) Pessimistic (b)
1
4
7
4
B Prepare Proposal Paper
CDE
Obtain Business License
MOF registration
A,B
A,B
Register with Companies Commission Malaysia
C,D
F
Audited Report
E
G
Obtain Tax Payment License
H
Obtain Business Premises License
D
E,F,G
1
Briefing
H
J
Interview
H
K
Roundtable Discussion
H
L
Acquire Tender
I,J,K
M
Complete Agreement of renting & Stamping
M
22226332HI
1
1
1
1
3544
7552233m
8
006627733
14
N
Proceed With Business
L
7
14
5452
21
QUESTIONS:
(a) Draw the project network.
(b) Apply PERT/CPM and provide the information or table on the ES, EF, LS, LF and
slack times for all the activities. What are the critical activities?
(c) What is the expected completion time for the project? What is the probability of
completing the project within this duration?
(d) What is the probability of completing this project within 49 days?
(e) In order to be 90% confident in meeting the deadline, how long should they allocate
to start establishing their business
(f) Is it possible to delay Activity J without affecting the project's completion time?
Why
Transcribed Image Text:Question 13: A group of final year students would like to start up their business on the campus of the university they are currently studying. They have consulted several owners of on-going business on the campus and have obtained the following information: Activity Description A Prepare Company Profile Immediate Time Estimates Predecessor Optimistic (a) Most Likely (m) Pessimistic (b) 1 4 7 4 B Prepare Proposal Paper CDE Obtain Business License MOF registration A,B A,B Register with Companies Commission Malaysia C,D F Audited Report E G Obtain Tax Payment License H Obtain Business Premises License D E,F,G 1 Briefing H J Interview H K Roundtable Discussion H L Acquire Tender I,J,K M Complete Agreement of renting & Stamping M 22226332HI 1 1 1 1 3544 7552233m 8 006627733 14 N Proceed With Business L 7 14 5452 21 QUESTIONS: (a) Draw the project network. (b) Apply PERT/CPM and provide the information or table on the ES, EF, LS, LF and slack times for all the activities. What are the critical activities? (c) What is the expected completion time for the project? What is the probability of completing the project within this duration? (d) What is the probability of completing this project within 49 days? (e) In order to be 90% confident in meeting the deadline, how long should they allocate to start establishing their business (f) Is it possible to delay Activity J without affecting the project's completion time? Why
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON