Quality Maintenance Machining Assem bly Total Control Budgeted overhead costs before allocation P350,000 P200,000 P400,000 P 300,000 P1,250,000 Budgeted machine hours 50,000 25,000 50,000 Budgeted direct labor hours 25,000 Budgeted hours of service: Quality Control Maintenance 21,000 35,000 40,000 7,000 7,000 12,000 10,000 18,000

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Using the direct method, the total amount of overhead allocated to each machine hour at NUBD Co. would be (round-off to 2 decimal places)

If NUBD Co. uses the step-down method of allocating service costs beginning with quality control, the maintenance costs allocated to the Assembly Department would be

If NUBD Co. uses the direct method of allocating service department costs, the total service costs allocated to the assembly department would be

If NUBD Co. uses the reciprocal method of allocating service costs, the total amount of quality control costs (rounded to the nearest peso) to be allocated to the other departments would be

The managers of NUBD Co. are discussing ways to allocate the cost of service departments such
as Quality Control and Maintenance to the production departments. To aid them in this discussion
the controller has provided the following information:
Quality
Control
Maintenance Machining Assembly
Total
Budgeted
overhead costs
before allocation
P 350,000
P200,000 P400,000
P300,000 P1,250,000
Budgeted
machine hours
50,000
25,000
50,000
Budgeted direct
labor hours
25,000
Budgeted hours
of service:
Quality Control
Maintenance
35,000
40,000
7,000
21,000
18,000
7,000
12,000
10,000
Transcribed Image Text:The managers of NUBD Co. are discussing ways to allocate the cost of service departments such as Quality Control and Maintenance to the production departments. To aid them in this discussion the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation P 350,000 P200,000 P400,000 P300,000 P1,250,000 Budgeted machine hours 50,000 25,000 50,000 Budgeted direct labor hours 25,000 Budgeted hours of service: Quality Control Maintenance 35,000 40,000 7,000 21,000 18,000 7,000 12,000 10,000
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education