PROJECT DATA FOR GMC ACADIA Activity Activity Time (weeks) Immediate Predecessor(s) START A 3 START В 4 START C 4 В 4 A E F 6 D, E G С, Е FINISH F, G B
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
Consider a project to produce custom door moldings for GMC Acadia cross-over vehicles, described in Table
a. If you start the project immediately, when will it be finished?
b. You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee A, currently assigned to activity G, to help Employee B, currently assigned to activity F. Each week that Employee A helps Employee B will result in activity G increasing its time by one week and activity F reducing its time by one week. How many weeks should Employee A work on activity F?
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images