Project A Project B Project C Project D Based on the data obtained from each project, you have found out the value of work done on the 31st of March, which is shown in Table 2 below. Project Table 1: The Planned Value of Work Done Schedule Feb March Jan 60,000 100,000 120,000 100,000 80,000 120,000 80,000 80,000 70,000 120,000 120,000 100,000 Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the 31st of March ABCD с April May 120,000 200,000 140,000 140,000 90,000 100,000 120,000 150,000 Actual Value of Work Done 300,000 250,000 250,000 280,000 Direct Cost Incurred 220,000 180,000 200,000 240,000 Each project is supposed to contribute 10% profit and 8% overhead to the company. You are requested to present to the company the turnover as of the 31st of March. Prepare your answer by answering. the following questions. a) Calculate the planned value of work. done, the total planned overhead and the total profit contribution from all the projects as of the 31st of March. b) Calculate the actual value of work done. and the total actual profit contribution from all the projects as of the 31st of March. c) Analyse planned and actual nett profit contribution of all the projects as of the 31st of March, and comment on the status of the projects. on the variance between the

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Table 1: The Planned Value of Work Done Schedule
Jan
Feb
March
Project A
Project B
Project C
Project D
60,000
100,000
80,000
120,000
100,000
80,000
80,000
120,000
120,000
120,000
70,000
100,000
April
120,000
140,000
90,000
120,000
Мay
200,000
140,000
100,000
150,000
Based on the data obtained from each project, you have found out the value of
work done on the 31st of March, which is shown in Table 2 below.
Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the
31st of March
Project
Actual Value of Work
Done
300,000
250,000
250,000
280,000
Direct Cost Incurred
A
220,000
180,000
200,000
240,000
Each project is supposed to contribute 10%
profit and 8% orerhead to the compoany.
You are requested to present to the
company the turnorer as of the 31st of
march. Prepare your answenr by answering
the following que'stions.
a) Calculate the planned ralue of work
done, the total planned orerhead and the
total profit contribution from all the.
projects as of the 31st of March.
b) Calculate the actual ralue of work done
and the totalactual profit contribution
from all the projects as of the 31st of
march.
c) Analyse
planned and actual nett profit
contribution of all the projects as of the
31stof march, and comment on the status
of the projects.
on the rariance between the
Transcribed Image Text:Table 1: The Planned Value of Work Done Schedule Jan Feb March Project A Project B Project C Project D 60,000 100,000 80,000 120,000 100,000 80,000 80,000 120,000 120,000 120,000 70,000 100,000 April 120,000 140,000 90,000 120,000 Мay 200,000 140,000 100,000 150,000 Based on the data obtained from each project, you have found out the value of work done on the 31st of March, which is shown in Table 2 below. Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the 31st of March Project Actual Value of Work Done 300,000 250,000 250,000 280,000 Direct Cost Incurred A 220,000 180,000 200,000 240,000 Each project is supposed to contribute 10% profit and 8% orerhead to the compoany. You are requested to present to the company the turnorer as of the 31st of march. Prepare your answenr by answering the following que'stions. a) Calculate the planned ralue of work done, the total planned orerhead and the total profit contribution from all the. projects as of the 31st of March. b) Calculate the actual ralue of work done and the totalactual profit contribution from all the projects as of the 31st of march. c) Analyse planned and actual nett profit contribution of all the projects as of the 31stof march, and comment on the status of the projects. on the rariance between the
Expert Solution
steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education