Problem 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost $206,800 $319,000 $361,еее $391,e00 Month Machine-Hours April May 120, e00 110,e00 130, e00 140, 000 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 110,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 88.000
Problem 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost $206,800 $319,000 $361,еее $391,e00 Month Machine-Hours April May 120, e00 110,e00 130, e00 140, 000 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 110,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 88.000
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
![Problem 3-15 High-Low Method; Predicting Cost [LO1, LO2]
Crosshill Company's total overhead costs at various levels of activity are presented below:
Total Overhead
Month
Machine-Hours
Cost
April
May
120,000
110, 000
130, 000
140, 000
$206, 800
$319,000
$361,000
$391, 000
June
July
Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the
110,000-machine-hour level of activity in May is as follows:
Utilities (variable)
Supervisory salaries (fixed)
Maintenance (mixed)
$ 88,000
25, 000
125, еее
Total overhead cost
$238, 000
The company wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $391,000 of overhead cost in July was maintenance cost. (Hint: To do this, first determine how much of
the $391,000 consisted of utilities and supervisory salaries. Think about the behaviour of variable and fixed costs within the relevant
range.) (Round the "Variable cost per unit" to 2 decimal places.)
Maintenance cost in July
2. Using the high-low method, estimate a cost formula for maintenance. (Round the "Variable cost per unit" to 2 decimal places.)
Machine- Hours
Maintenance Cost
High activity level
Low activity level
Change
2$
Variable cost element
per MH
Fixed cost element](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F03eecdbf-da19-4f5c-a265-cf269087e6dd%2Fa8088c00-0fcb-4b76-8b38-1efcc52a764e%2Fnhbwpl_processed.png&w=3840&q=75)
Transcribed Image Text:Problem 3-15 High-Low Method; Predicting Cost [LO1, LO2]
Crosshill Company's total overhead costs at various levels of activity are presented below:
Total Overhead
Month
Machine-Hours
Cost
April
May
120,000
110, 000
130, 000
140, 000
$206, 800
$319,000
$361,000
$391, 000
June
July
Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the
110,000-machine-hour level of activity in May is as follows:
Utilities (variable)
Supervisory salaries (fixed)
Maintenance (mixed)
$ 88,000
25, 000
125, еее
Total overhead cost
$238, 000
The company wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $391,000 of overhead cost in July was maintenance cost. (Hint: To do this, first determine how much of
the $391,000 consisted of utilities and supervisory salaries. Think about the behaviour of variable and fixed costs within the relevant
range.) (Round the "Variable cost per unit" to 2 decimal places.)
Maintenance cost in July
2. Using the high-low method, estimate a cost formula for maintenance. (Round the "Variable cost per unit" to 2 decimal places.)
Machine- Hours
Maintenance Cost
High activity level
Low activity level
Change
2$
Variable cost element
per MH
Fixed cost element

Transcribed Image Text:Y =
3. Express the company's total overhead cost in the form Y = a + bX. (Round the "Variable cost per unit" to 2 decimal places.)
Variable Cost per
Fixed Cost
Machine-Hour
Utilities cost
Supervisory salaries cost
Maintenance cost
Total overhead cost
0.00
Y =
4. What total overhead cost would you expect to be incurred at an activity level of 78,000 machine-hours? (Round the "Variable cost
per unit" to 2 decimal places.)
Total overhead cost
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,


Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,

Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON

Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education