Please redo this problem and show me steps on how to get the following questions correct, its stating I am wrong. Please help Direct Labor Variances The following data relate to labor cost for production of 6,600 cellular telephones: Actual: 4,480 hrs. at $16.10 $72,128 Standard: 4,410 hrs. at $16.40 $72,324 a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter all values as a positive number and then identify the variance (e.g. Favorable or Unfavorable) in the adjacent column. Rate variance $ Favorable Time variance $ Unfavorable Total direct labor cost variance $ Favorable b. The employees may have been less-experienced or poorly trained, thereby resulting in a lower labor rate than planned. The lower level of experience or training may have resulted in less efficient performance. Thus, the actual time required was more than standard. LIz C
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Please redo this problem and show me steps on how to get the following questions correct, its stating I am wrong. Please help
Direct Labor Variances
The following data relate to labor cost for production of 6,600 cellular telephones:
Actual: | 4,480 hrs. at $16.10 | $72,128 |
Standard: | 4,410 hrs. at $16.40 | $72,324 |
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter all values as a positive number and then identify the variance (e.g. Favorable or Unfavorable) in the adjacent column.
Rate variance | $ | Favorable |
Time variance | $ | Unfavorable |
Total direct labor cost variance | $ | Favorable |
b. The employees may have been less-experienced or poorly trained, thereby resulting in a lower labor rate than planned. The lower level of experience or training may have resulted in less efficient performance. Thus, the actual time required was more than standard.
LIz C
Trending now
This is a popular solution!
Step by step
Solved in 6 steps with 4 images