On March 1, 2025, Pharoah Construction Company contracted to construct a factory building for Bloom Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Bloom for 2025, 2026, and 2027 are given below. 2025 2026 2027 Contract costs incurred during the year $2,662,800 $2,188,000 $2,389,200 Estimated costs to complete the contract at 12/31 Billings to Bloom during the year 3,180,000 3,677,200 2,389,200 3,480,000 -0- 1,670,000 (a1) Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2025 LA %

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 9MC
icon
Related questions
Question
On March 1, 2025, Pharoah Construction Company contracted to construct a factory building for Bloom Manufacturing Inc. for a total
contract price of $8,330,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to
complete the contract, and accumulated billings to Bloom for 2025, 2026, and 2027 are given below.
2025
2026
2027
Contract costs incurred during the year
$2,662,800
$2,188,000 $2,389,200
Estimated costs to complete the contract at 12/31
Billings to Bloom during the year
3,180,000
3,677,200 2,389,200
3,480,000
-0-
1,670,000
(a1)
Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this
contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank.
Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2025
LA
%
Transcribed Image Text:On March 1, 2025, Pharoah Construction Company contracted to construct a factory building for Bloom Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2027. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Bloom for 2025, 2026, and 2027 are given below. 2025 2026 2027 Contract costs incurred during the year $2,662,800 $2,188,000 $2,389,200 Estimated costs to complete the contract at 12/31 Billings to Bloom during the year 3,180,000 3,677,200 2,389,200 3,480,000 -0- 1,670,000 (a1) Using the percentage-of-completion method, prepare a schedule to compute the profit or loss to be recognized as a result of this contract for the year ended December 31, 2025. (Ignore income taxes.) (If answer is 0, please enter O. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2025 LA %
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage