On January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year 12/31/2021 12/31/2022 12/31/2023 ? ? P 3740000 P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
On January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of
P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided
to employ cost to cost method. The following data are provided by the accountant and project manager
concerning the construction costs for the three years of construction:
Year
12/31/2021 12/31/2022 12/31/2023
P 3740000
Costs incurred during the year
Realized gross profit/(loss) during the year
Percentage of completion as of the end of the year
?
?
P750,000 (P250,000) (P800,000)
50%
37.5%
?
What is the balance of Construction in Progress on December 31, 2023?
Transcribed Image Text:On January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year 12/31/2021 12/31/2022 12/31/2023 P 3740000 Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year ? ? P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education