Using the following information for a project, prepare a work in progress schedule to answer the questions that follow • Contract Amount: $858,750 • Original Estimated Cost: $815,000 • Billed to Date: $295,000 • Payments Received to Date: $265,500 • Cost incurred to Date: $250,000 • Estimated Cost to Complete: $575,000 • Cost Paid to Date: $180,000 Provide Answers to the following questions. Round all dollar answers to the nearest whole dollar (i.e. $215,850) and round all percentages to the nearest hundredth (i.e. 15.24%) • Current Re-estimated Total Cost: • Estimated Gross Profit at Completion: • Percentage of Completion: • Total Gross Profit (Loss) to Date: • Amount Earned to Date: • Over Billings: • Under Billings: Remaining Billings: • Job Borrow:

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Using the following information for a project, prepare a work in progress schedule to answer the
questions that follow
• Contract Amount: $858,750
• Original Estimated Cost: $815,000
• Billed to Date: $295,000
• Payments Received to Date: $265,500
• Cost incurred to Date: $250,000
• Estimated Cost to Complete: $575,000
• Cost Paid to Date: $180,000
Provide Answers to the following questions. Round all dollar answers to the nearest whole dollar
(i.e. $215,850) and round all percentages to the nearest hundredth (i.e. 15.24%)
• Current Re-estimated Total Cost:
• Estimated Gross Profit at Completion:
Percentage of Completion:
• Total Gross Profit (Loss) to Date:
• Amount Earned to Date:
• Over Billings:
• Under Billings:
Remaining Billings:
• Job Borrow:
Transcribed Image Text:Using the following information for a project, prepare a work in progress schedule to answer the questions that follow • Contract Amount: $858,750 • Original Estimated Cost: $815,000 • Billed to Date: $295,000 • Payments Received to Date: $265,500 • Cost incurred to Date: $250,000 • Estimated Cost to Complete: $575,000 • Cost Paid to Date: $180,000 Provide Answers to the following questions. Round all dollar answers to the nearest whole dollar (i.e. $215,850) and round all percentages to the nearest hundredth (i.e. 15.24%) • Current Re-estimated Total Cost: • Estimated Gross Profit at Completion: Percentage of Completion: • Total Gross Profit (Loss) to Date: • Amount Earned to Date: • Over Billings: • Under Billings: Remaining Billings: • Job Borrow:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education