Under the percentage-of-completion method, calculate the construction costs to be expensed in 2024. Construction cost expensed in 2024 1945800
Under the percentage-of-completion method, calculate the construction costs to be expensed in 2024. Construction cost expensed in 2024 1945800
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
Please help me.
Thankyou.
![* Your answer is incorrect.
Under the percentage-of-completion method, calculate the construction costs to be expensed in 2024.
Construction cost expensed in 2024
eTextbook and Media
List of Accounts
$
1945800](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff7373726-0d35-46ca-aa27-97bcf9126f3a%2F42e6e2a1-264b-4d36-9bda-fa4a5568a460%2Fnm6bxc_processed.jpeg&w=3840&q=75)
Transcribed Image Text:* Your answer is incorrect.
Under the percentage-of-completion method, calculate the construction costs to be expensed in 2024.
Construction cost expensed in 2024
eTextbook and Media
List of Accounts
$
1945800
![Assume that Ivanhoe Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of
$4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the
construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
Estimated loss
2023
$1,035,000
3,105,000
955,000
788,000
*$2,980,800+$1.676,700
2024
$2,980,800
1,676,700
2,443,000
The revised estimates for the bridge contract are as follows.
1,801,000
2025
$4,657,500
1,202,000
2023 Original Estimates 2024 Revised Estimates
$4,600,000
4,140,000
$460,000
2,011,000
0
$4,600,000
4,657.500*
$(57,500)](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff7373726-0d35-46ca-aa27-97bcf9126f3a%2F42e6e2a1-264b-4d36-9bda-fa4a5568a460%2Fncaz8fg_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Assume that Ivanhoe Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of
$4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the
construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
Estimated loss
2023
$1,035,000
3,105,000
955,000
788,000
*$2,980,800+$1.676,700
2024
$2,980,800
1,676,700
2,443,000
The revised estimates for the bridge contract are as follows.
1,801,000
2025
$4,657,500
1,202,000
2023 Original Estimates 2024 Revised Estimates
$4,600,000
4,140,000
$460,000
2,011,000
0
$4,600,000
4,657.500*
$(57,500)
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education