(B) construction of the shopping complex commenced on 01st April 2017. The following information relates to this construction contract for the year ended 31st March 2018: MNR Construction Ltd. started to construct a shopping complex and the Rs. Material issued to the site 5,600,000 Direct wages paid 1,800,000 Material returned from the site 250,000 Plant and machinery installed (on 01st April 2017) 10,000,000 Material at site as at 31st March 2018 1.200,000 Plant and machinery are depreciated at 10% per annum on the straight-line basis. You are required to: Recognize the cost of the contract as at 31st March 2018

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
MNR Construction Ltd. started to construct a shopping complex and the
construction of the shopping complex commenced on 01st April 2017. The following
information relates to this construction contract for the year ended 31st March 2018:
(B)
Rs. Material issued to the site
5,600,000
Direct wages paid
1,800,000
Material returned from the site
250,000
Plant and machinery installed (on 01st April 2017)
10,000,000
Material at site as at 31st March 2018
1,200,000
Plant and machinery are depreciated at 10% per annum on the straight-line basis.
You are required to: Recognize the cost of the contract as at 31st March 2018
Transcribed Image Text:MNR Construction Ltd. started to construct a shopping complex and the construction of the shopping complex commenced on 01st April 2017. The following information relates to this construction contract for the year ended 31st March 2018: (B) Rs. Material issued to the site 5,600,000 Direct wages paid 1,800,000 Material returned from the site 250,000 Plant and machinery installed (on 01st April 2017) 10,000,000 Material at site as at 31st March 2018 1,200,000 Plant and machinery are depreciated at 10% per annum on the straight-line basis. You are required to: Recognize the cost of the contract as at 31st March 2018
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education