Mabel’s Ceramics spent $3000 on a new kiln last year, in the belief that it would cut energy usage 25% over the old kiln. This kiln is an oven that turns “greenware” into finished pottery. Mabel is concerned that the new kiln requires extra labor hours for its operation. Mabel wants to check the energy savings of the new oven, and also to look over other measures of their productivity to see if the change really was beneficial. Mabel has the following data to work with: The year before Year just ended Production (finished units) 4000 4100 Labor (hrs) 350 375 Capital ($) 15000 18000 Energy (kWh) 3000 2600 Also, suppose that the average labor cost is $12 per hour and cost of energy is $0.40 per kwh. a. Were the modifications beneficial? (Compute labor, energy, and capital productivity for the two years and compare.) b. Compute percentage change in multi-factor productivity of the year just ended from that of year before. c. If the multifactor productivity must be restored next year to what is was the year before, assuming the same output next year as the year just ended, by how the input must be reduced from what it is this year?

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question

PROBLEMS
1.
Mabel’s Ceramics spent $3000 on a new
kiln last year, in the belief that it would cut energy usage 25% over the old
kiln. This kiln is an oven that turns “greenware” into finished
pottery. Mabel is concerned that the new kiln requires extra labor hours for
its operation. Mabel wants to check the energy savings of the new oven, and
also to look over other measures of their productivity to see if the change
really was beneficial. Mabel has the following data to work with:

The
year before

Year
just ended

Production (finished units)

4000

4100

Labor (hrs)

350

375

Capital ($)

15000

18000

Energy (kWh)

3000

2600

Also, suppose that the average labor
cost is $12 per hour and cost of energy is $0.40 per kwh.
a.
Were the modifications beneficial? (Compute labor, energy, and capital
productivity for the two years and compare.)
b.
Compute percentage change in
multi-factor productivity of the year just ended from that of year before.
c.
If the multifactor productivity must be
restored next year to what is was the year before, assuming the same output
next year as the year just ended, by how the input must be reduced from what it
is this year?

2.
An Appliance Service company made house calls
and repaired 10 lawn-mowers, 2 refrigerators, and 3 washers in an 8-hour day
with his standard crew of 3 workers. The
retail price for each respective service is $50, $200, and $120. The average wage for the workers is $12 per
hour. The materials cost for a day was
$200 while the overhead cost was $50.
a. What is the company’s labor productivity?
b. What is the multifactor productivity?
c. How much of a reduction in input is
necessary for a 5% increase in multifactor productivity?

3.
Consider
the tasks, durations, and predecessor relationships in the following network.
Draw the AON network and answer the questions that follow.

Activity Description

Immediate
Predecessor(s)

Optimistic
(Weeks)

Most Likely
(Weeks)

Pessimistic
(Weeks)

A

4

7

10

B

A

2

8

20

C

A

8

12

16

D

B

1

2

3

E

D, C

6

8

22

F

C

2

3

4

G

F

2

2

2

H

F

6

8

10

I

E, G

4

8

12

J

I

1

2

3

a.
Schedule the activities of this project
and determine (i) the expected project completion time, (ii) the earliest and
latest start and finish times, and the slack for all the activities, and (iii)
all the critical paths.
b.
What is the probability of completion of
the project before week 42?
c.
What is the probability of completion of
the project before week 35?
d.
With 99% confidence what is your
estimate for the project completion time.

4.
Consider
the following project. All activity
times are in weeks.

Activity

Immediate
Predecessor(s)

Normal Time

Crash time

Normal cost

Crash cost

A

7

4

20000

38000

B

8

5

50000

74000

C

A

9

7

80000

110000

D

A, B

8

8

30000

30000

E

B

9

8

10000

12000

F

C

10

8

90000

124000

G

D, E

5

5

25000

25000

H

E

10

8

32000

40000

I

F, G

5

4

28000

35000

a.
Draw an AON network.
b.
Identify all the unique paths from
start to finish and determine the critical path, normal project completion
time, and normal project cost.
c.
Compute MTR, Cost of
crashing/week.
d.
Which activity would you crash
first and by how many weeks?
e.
Determine the project time and
cost after crashing the activity selected in (d).

5.
Consider
the following CPM Solver model.
.jpg”>

a) Determine the successor activities in cells
I2 to I10.
b) Determine the Excel formulas for the following
cells: F2, G2, C15, C18, D18, D21, C25, G19, G16, G15, H15, B27, B28, and B29.
c) What is the Solver Target cell for
minimizing the project completion time?
d) What is the Solver changing cell range?
e) What are the Solver constraints?

Expert Solution
steps

Step by step

Solved in 5 steps with 11 images

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,