Klassen Toy Company, Ic., assembles two parts (parts 1 and 2): Part 1 is first processed at workstation A for 12 minutes per unit and then processed at workstation B for 30 minutes per unit. Part 2 is simultaneously processed at workstation C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D, where the two parts are assembled. The time at workstation D is 10 minutes. a) The bottleneck of this process is workstation B , at 30 minutes per unit (enter your response as a whole number). b) The hourly capacity of the process is units (enter your response as a whole number).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

h4q3b

**Klassen Toy Company, Inc. Process Overview:**

Klassen Toy Company, Inc., assembles two parts (parts 1 and 2):

- **Part 1** is processed at:
  - **Workstation A:** 12 minutes per unit
  - **Workstation B:** 30 minutes per unit

- **Part 2** is simultaneously processed at:
  - **Workstation C:** 20 minutes per unit

- Workstations B and C feed the parts to an assembler at:
  - **Workstation D:** Where both parts are assembled in 10 minutes

**Key Points:**

a) **Bottleneck Identification:**
   - The bottleneck of the process is **workstation B**, with a processing time of **30 minutes per unit**.

b) **Hourly Capacity Calculation:**
   - The hourly capacity of the process needs to be calculated. Provide your response as a whole number.
Transcribed Image Text:**Klassen Toy Company, Inc. Process Overview:** Klassen Toy Company, Inc., assembles two parts (parts 1 and 2): - **Part 1** is processed at: - **Workstation A:** 12 minutes per unit - **Workstation B:** 30 minutes per unit - **Part 2** is simultaneously processed at: - **Workstation C:** 20 minutes per unit - Workstations B and C feed the parts to an assembler at: - **Workstation D:** Where both parts are assembled in 10 minutes **Key Points:** a) **Bottleneck Identification:** - The bottleneck of the process is **workstation B**, with a processing time of **30 minutes per unit**. b) **Hourly Capacity Calculation:** - The hourly capacity of the process needs to be calculated. Provide your response as a whole number.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.