Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of September but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the total cost of the job when it is completed in October? A. $16,000 B. $22,500 C. $37,000 D. $26,500 E. $32,000

Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter4: Accounting For Factory Overhead
Section: Chapter Questions
Problem 17P: Luna Manufacturing Inc. completed Job 2525 on May 31, and there were no jobs in process in the...
icon
Related questions
Question

Hi expart Provide solution for this accounting question

Job A3B was ordered by a customer on September 25. During the
month of September, Jaycee Corporation requisitioned $2,500 of
direct materials and used $4,000 of direct labor. The job was not
finished by the end of September but needed an additional $3,000 of
direct materials and additional direct labor of $6,500 to finish the job
in October. The company applies overhead at the end of each month
at a rate of 200% of the direct labor cost incurred. What is the total
cost of the job when it is completed in October?
A. $16,000
B. $22,500
C. $37,000
D. $26,500
E. $32,000
Transcribed Image Text:Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of September but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the total cost of the job when it is completed in October? A. $16,000 B. $22,500 C. $37,000 D. $26,500 E. $32,000
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,