Instructions: Assignment must be completed professionally, spell and grammar checked, and well written with a logical flow. Question 1: Refer to the network below Baseline schedule 0,6 6,10 10,15 A F 6 4 5 0,6 6,10 15,20 0,2 2,9 10,20 20,28 28,30 PS B E G H J 2 7 10 8 2 1,3 3,10 10,20 20,28 28,30 0 0,9 20,23 с 9 11,20 3 B 25,28 Activity Duration IPA ES EF LS LF TF FF A 6 0 6 0 6 0 0 B 2 - 0 2 1 3 1 0 с 9 - 0 9 11 20 11 0 D 4 A, B 6 10 6 10 0 0 E 7 B 2 9 3 10 1 1 F 5 D 10 15 15 20 5 5 G 10 D, E 10 20 10 20 0 0 H 8 C, F, 20 28 20 28 0 0 G | 3 C, G 20 23 25 28 5 5 2 H, I 28 30 28 30 0 0 Fifteen days after the start of the project, the following information is received. Activity A Completed 2 days later than planned Activity B Completed on time Activity C Started; 4 days left • Activity D Completed; took 5 days to finish Activity E Completed Activity F Canceled Activity G Started 3 days late; project manager hopes to cut 1 day of its duration Activity K Added: Duration = 4 days. IPA = C Activity L Added: Duration = 3 days. IPA = K, G Activity | Adjusted: IPA = L
Instructions: Assignment must be completed professionally, spell and grammar checked, and well written with a logical flow. Question 1: Refer to the network below Baseline schedule 0,6 6,10 10,15 A F 6 4 5 0,6 6,10 15,20 0,2 2,9 10,20 20,28 28,30 PS B E G H J 2 7 10 8 2 1,3 3,10 10,20 20,28 28,30 0 0,9 20,23 с 9 11,20 3 B 25,28 Activity Duration IPA ES EF LS LF TF FF A 6 0 6 0 6 0 0 B 2 - 0 2 1 3 1 0 с 9 - 0 9 11 20 11 0 D 4 A, B 6 10 6 10 0 0 E 7 B 2 9 3 10 1 1 F 5 D 10 15 15 20 5 5 G 10 D, E 10 20 10 20 0 0 H 8 C, F, 20 28 20 28 0 0 G | 3 C, G 20 23 25 28 5 5 2 H, I 28 30 28 30 0 0 Fifteen days after the start of the project, the following information is received. Activity A Completed 2 days later than planned Activity B Completed on time Activity C Started; 4 days left • Activity D Completed; took 5 days to finish Activity E Completed Activity F Canceled Activity G Started 3 days late; project manager hopes to cut 1 day of its duration Activity K Added: Duration = 4 days. IPA = C Activity L Added: Duration = 3 days. IPA = K, G Activity | Adjusted: IPA = L
Residential Construction Academy: House Wiring (MindTap Course List)
4th Edition
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Gregory W Fletcher
Chapter12: Raceway Installation
Section: Chapter Questions
Problem 10RQ
Related questions
Question
Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any.
- New network based on the new information received after 15 days (Correct calculations, professionally done).
- Mention if critical path changes or extended.
- Write causes for change in critical path or extension in the critical path.

Transcribed Image Text:Instructions: Assignment must be completed professionally, spell and grammar checked, and well written with
a logical flow.
Question 1:
Refer to the network below
Baseline schedule
0,6
6,10
10,15
A
F
6
4
5
0,6
6,10
15,20
0,2
2,9
10,20
20,28
28,30
PS
B
E
G
H
J
2
7
10
8
2
1,3
3,10
10,20
20,28
28,30
0
0,9
20,23
с
9
11,20
3
B
25,28
Activity Duration IPA
ES
EF
LS
LF
TF
FF
A
6
0
6
0
6
0
0
B
2
-
0
2
1
3
1
0
с
9
-
0
9
11
20
11
0
D
4
A, B
6
10
6
10
0
0
E
7
B
2
9
3
10
1
1
F
5
D
10
15
15
20
5
5
G
10
D, E
10
20
10
20
0
0
H
8
C, F,
20
28
20
28
0
0
G
|
3
C, G
20
23
25
28
5
5
2
H, I
28
30
28
30
0
0
Fifteen days after the start of the project, the following information is received.
Activity A Completed 2 days later than planned
Activity B Completed on time
Activity C Started; 4 days left
• Activity D Completed; took 5 days to finish
Activity E Completed
Activity F Canceled
Activity G Started 3 days late; project manager hopes to cut 1 day of its duration
Activity K Added: Duration = 4 days. IPA = C
Activity L Added: Duration = 3 days. IPA = K, G
Activity | Adjusted: IPA = L
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images

Recommended textbooks for you

Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning

Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning

Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning

Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning

Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,