In three (3) days, your endeavor will begin Masonry Works. In accordance with this, you must calculate (ahead of time) the total number of CHB sections required for the road-facing exterior walls. To ensure you have sufficient materials, you added an allowance for eight percent (8%) breakage. Determine the quantity of CHB to be ordered. Round your answer to the nearest integer. Student Number is the Total Contract Price (TCP) of the Undertaking. If the project's operating expenses are 35% of the total budget, how much will be left if the price of CHB is 13 pesos and 16 pesos, respectively? use 123456 as the TCP.
You are the Field Engineer and Cost Engineer for a residential project that you are managing. In three (3) days, your endeavor will begin Masonry Works. In accordance with this, you must calculate (ahead of time) the total number of CHB sections required for the road-facing exterior walls.
To ensure you have sufficient materials, you added an allowance for eight percent (8%) breakage.
Determine the quantity of CHB to be ordered. Round your answer to the nearest integer.
Student Number is the Total Contract Price (TCP) of the Undertaking. If the project's operating expenses are 35% of the total budget, how much will be left if the price of CHB is 13 pesos and 16 pesos, respectively?
use 123456 as the TCP.
Below are specifics:
NEED ASAP 30 MINS
Step by step
Solved in 3 steps