In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is worki Immediate Predecessor(s) Time (days) 5 4 6 6 4 4 6 8 Carl's team should be able to complete the project in days. Critical path activities for Carl's project are Activity A B с D G H AABBCD E, F

Algebra: Structure And Method, Book 1
(REV)00th Edition
ISBN:9780395977224
Author:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Chapter2: Working With Real Numbers
Section2.3: Rules For Addition
Problem 8P
icon
Related questions
Question
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:
Immediate Predecessor(s)
Carl's team should be able to complete the project in
Critical path activities for Carl's project are
days.
Activity
ABCDELI
А
с
F
G
H
A AB BCD
В
С
E, F
Time (days)
446 54
6
6
4
8
Transcribed Image Text:In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Immediate Predecessor(s) Carl's team should be able to complete the project in Critical path activities for Carl's project are days. Activity ABCDELI А с F G H A AB BCD В С E, F Time (days) 446 54 6 6 4 8