In February 2020, Sheridan Construction signed a contract and commenced construction on a parking garage. The total contract price was $88.3 million and was expected to be completed in July 2024 at a total estimated cost of $81.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sheridan’s year-end was September 30. By the end of September, 2020, Sheridan had incurred $20,250,000 in costs and had invoiced $7,600,000 in progress billings. $7,100,000 of the progress billings had been collected. By September 30, 2021, Sheridan had incurred $39,000,000 in total costs and had invoiced $45,100,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,900,000 in total had been collected. Also, Sheridan reviewed its cost estimates on the project, and now believed the parking garage would cost $78.0 million in total to complete. Prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.) No. Account Titles and Explanation Debit Credit 1. (To record the 2020 cost of construction) 2. (To record the 2020 progress billings) 3. (To record the 2020 cash collections) 4. (To record the 2020 revenue) 5.
In February 2020, Sheridan Construction signed a contract and commenced construction on a parking garage. The total contract price was $88.3 million and was expected to be completed in July 2024 at a total estimated cost of $81.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sheridan’s year-end was September 30. By the end of September, 2020, Sheridan had incurred $20,250,000 in costs and had invoiced $7,600,000 in progress billings. $7,100,000 of the progress billings had been collected. By September 30, 2021, Sheridan had incurred $39,000,000 in total costs and had invoiced $45,100,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,900,000 in total had been collected. Also, Sheridan reviewed its cost estimates on the project, and now believed the parking garage would cost $78.0 million in total to complete. Prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.) No. Account Titles and Explanation Debit Credit 1. (To record the 2020 cost of construction) 2. (To record the 2020 progress billings) 3. (To record the 2020 cash collections) 4. (To record the 2020 revenue) 5.
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
100%
In February 2020, Sheridan Construction signed a contract and commenced construction on a parking garage. The total contract price was $88.3 million and was expected to be completed in July 2024 at a total estimated cost of $81.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project during the construction process. Sheridan’s year-end was September 30.
By the end of September, 2020, Sheridan had incurred $20,250,000 in costs and had invoiced $7,600,000 in progress billings. $7,100,000 of the progress billings had been collected.
By September 30, 2021, Sheridan had incurred $39,000,000 in total costs and had invoiced $45,100,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,900,000 in total had been collected. Also, Sheridan reviewed its cost estimates on the project, and now believed the parking garage would cost $78.0 million in total to complete.
By the end of September, 2020, Sheridan had incurred $20,250,000 in costs and had invoiced $7,600,000 in progress billings. $7,100,000 of the progress billings had been collected.
By September 30, 2021, Sheridan had incurred $39,000,000 in total costs and had invoiced $45,100,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,900,000 in total had been collected. Also, Sheridan reviewed its cost estimates on the project, and now believed the parking garage would cost $78.0 million in total to complete.
Prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
No.
|
Account Titles and Explanation
|
Debit
|
Credit
|
1.
|
|
|
|
|
|
||
(To record the 2020 cost of construction)
|
|||
2.
|
|
|
|
|
|
||
(To record the 2020 progress billings)
|
|||
3.
|
|
|
|
|
|
||
(To record the 2020 cash collections)
|
|||
4.
|
|
|
|
|
|
||
(To record the 2020 revenue)
|
|||
5.
|
|
|
|
|
|
|
|
(To record the construction expenses)
|
List of Accounts
Prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
No
|
Account Titles and Explanation
|
Debit
|
Credit
|
1.
|
|
|
|
|
|
||
(To record the 2021 cost of construction)
|
|||
2.
|
|
|
|
|
|
||
(To record the 2021 progress billings)
|
|||
3.
|
|
|
|
|
|
||
(To record the 2021 cash collections)
|
|||
4.
|
|
|
|
|
|
||
(To record the 2021 revenue)
|
|||
5.
|
|
|
|
|
|
|
|
(To record the 2021 expenses)
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education