In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,100,000 4,900,000 2, 200,000 1,900, 000 $2,450,000 $2,695,000 2,450,000 2,350,000 2,300,000 5,450,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion.
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution: Gross profit for the year = Revenue for the current period - Expense for the current…
Q: Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the…
A: In completed contract method, revenue and profit are recognized only on completion if contract.…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Requirement 4 : 2018 2019 2020 Revenue $ 2,800,000 $ 3,692,964 $…
Q: [The following information applies to the questions displayed below.] In 2024, the Westgate…
A: Accounting to the question given, we need to prepare the partial balance sheet of Westgate…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Project reports and financial statements frequently include information on the expected cost of…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: If the organization uses the percentage of completion approach, the construction contract is a…
Q: Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years…
A: Given that: Full contract price = $10,000,000
Q: Journal entry worksheet 2 3 4 Record gross profit (loss). Note: Enter debits before credits. Date…
A: Journal entry refers to recording and classifying business transactions initially into books of…
Q: Required: 1. Prepare journal entries to recognize revenue for 2018, 2019 and 2020. I
A: In Year 2018 Construction contract price: $8,360,000 %age completion= $2,120,000…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Construction contracts are the long-term contract because the work of construction generally takes…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution 1: Amount of revenue and gross profit (loss) to be organized in each of three years using…
Q: 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: ) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: BS termed as Balance sheet which is one of vital financial statements of the business as this states…
Q: Required information [The following information applies to the questions displayed below.] In 2024,…
A: Part 2: Explanation:Step 1: Calculate the total estimated costs of the project.Total estimated costs…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: In the case of construction contracts revenue and gross profit are recognized on the basis of the…
Q: Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod…
A: Revenue is recognized under a construction contract at different stages as agreed in the contract.…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: 2018 2019 2020 Revenue 3000000 3500000 35000000 Gross profit (loss) 360000 1200000 574000
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: To calculate the amount of revenue and gross profit (loss) to be recognized in each of the three…
Q: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three…
A: Percentage of completion method refers to a method which is used to report the expenses and revenues…
Q: 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three…
A: In the 'completed contract method' of revenue recognition, all the revenue and profit of contract…
Q: Required information [The following information applies to the questions displayed below.] In 2024,…
A: The question is based on the concept of Financial Accounting.In case of construction contracts…
Q: Required information [The following information applies to the questions displayed below.] In 2021,…
A: The construction cost is usually recorded in proportion to the cost actually incurred and how much…
Q: n 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: The question is based on the concept of Financial Accounting. Construction contracts are the…
Q: Required information [The following information applies to the questions displayed below.) In 2024,…
A: The question is based on the concept of Financial Accounting.In construction contracts revenue and…
Q: Assume that Blossom Construction Company has a non-cancellable contract to construct a $5,400,000…
A: The completed contract method of revenue recognition refers to an accounting procedure in which all…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Part 2: ExplanationStep 1: Calculate the percentage of completion for each year using the formula:\[…
Q: Required information Skip to question [The following information applies to the questions displayed…
A: The objective of the question is to prepare the necessary journal entries for the years 2024, 2025,…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Gross profit refers to a company's earnings after deducting the costs of producing and selling its…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Gross profit for the year = Revenue for the current period - Expense for the current period
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution: Under percentage of completion method of revenue recognition for long term construction…
Q: In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: In the case of construction contracts revenue and gross profit are recognized on the basis of the…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: In contract costing the percentage of completion method is used and the revenue is recognized by…
Q: Required information [The following information applies to the questions displayed below.] In 2024,…
A: Revenue computation for long-term contracts requires special treatment than other normal revenue as…
Q: Required information Skip to question [The following information applies to the questions displayed…
A: The objective of the question is to prepare the necessary journal entries for the years 2024, 2025,…
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,344,000 $ 3,960,000 $ 1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 0 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.Required:1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries…Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 Cost incurred during the year Estimated costs to complete as of year-end $ 2,400,000 5,600,000 2,000,000 Billings during the year Cash collections during the year 1,800,000 Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress Add: Billings Current liabilities: Billings in excess of CIP 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. $ 2024 900,000 2,000,000 $4,285,714 (1,100,000) $ 2,070,000 0 2025 $ 3,600,000 2,000,000 4,000,000 3,600,000 2025…! Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 Cost incurred during the year $ 2,156,000 Estimated costs to complete as of year-end 5,544,000 Billings during the year 2,130,000 2025 $3,388,000 2,156,000 3,414,000 2026 $2,371,600 0 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Revenue Gross profit (loss) 2024 I.. 2025 2026
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2024 $ 2,739,000 5,561,000 2,300,000 2,100,000 Cost incurred during the year Estimated costs to complete as of year-end 2025 $ 3,735,000 1,826,000 4,174,000 3,900,000 2024 $ 2,430,000 5,630,000 2-b. In the journal below, complete the necessary journal entries for the year…6) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred…Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,100,000 2023 $2,695,000 2022 $2,450,000 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. Ø 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for…
- Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2024 $ 2,184,000 5,616,000 2,120,000 1,860,000 2024 2025 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus…In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to percentage of completion. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).2-c. In the journal below, complete the necessary journal entries for the year 2023…Required information [The following information applies to the questions displayed below] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,100,000 2022 $3,150,000 2023 $2,475,000 5,400,000 2,150,000 2,250,000 3,100,000 8 1,875,000 3,100,000 4,750,000 5,025,000 Westgate recognizes revenue over time according to percentage of completion. 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Balance Sheet (Partial) Current assets Current liabilities: 2021 2022 0 0
- Assume that Crane Construction Company has a non-cancellable contract to construct a $4,640,000 bridge at an estimated cost of $4,176,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. (Note that, by the end of 2024, Crane has revised the estimated total cost from $4,176,000 to $4,228,200.) Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year (a1) Account Titles and Explanation (To record cost of construction) (To record progress billings) (To record collections) (To record revenues) 2023 (To record construction expense) 3,173,760 $1,002,240 $2,959,740 $4,228,200 994,000 2024 834,960 1,268,460 2,483,000 Prepare all journal entries required for Crane to account for this contract for 2023. (Credit account titles are automatically indented when the amount is entered. Do not…! Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 $ 2,580,000 $ 4,042,000 6,020,000 1,978,000 4,562,000 2,060,000 1,830,000 4,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2026 $ 2,175,800 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. 0 3,378,000 3,970,000Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2021 2022 $2,610,000 $3,162,000 6,390,000 2,028,000 2,100,000 1,850,000 2021 2022 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) 2023 $2,230,800 2023 0 3,672,000 4,228,000 5,150,000 3,000,000