Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $ 2,400,000 5,600,000 2,000,000 1,800,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2025 $3,600,000 2,000,000 4,000,000 3,600,000 2026 $ 2,200,000 0 4,000,000 4,600,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Required information
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024
Cost incurred during the year
Estimated costs to complete as of year-end
$ 2,400,000
5,600,000
2,000,000
Billings during the year
Cash collections during the year
1,800,000
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Accounts receivable
Construction in progress
Add: Billings
Current liabilities:
Billings in excess of CIP
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the
contract.
Note: Do not round intermediate calculations.
$
2024
900,000
2,000,000
$4,285,714
(1,100,000)
$ 2,070,000
0
2025
$ 3,600,000
2,000,000
4,000,000
3,600,000
2025
2026
$ 2,200,000
0
0
4,000,000
4,600,000
Transcribed Image Text:Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 Cost incurred during the year Estimated costs to complete as of year-end $ 2,400,000 5,600,000 2,000,000 Billings during the year Cash collections during the year 1,800,000 Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress Add: Billings Current liabilities: Billings in excess of CIP 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. $ 2024 900,000 2,000,000 $4,285,714 (1,100,000) $ 2,070,000 0 2025 $ 3,600,000 2,000,000 4,000,000 3,600,000 2025 2026 $ 2,200,000 0 0 4,000,000 4,600,000
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education