Required Information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2822 $2,300,000 2,660,000 2,860,000 5,060,000 5,360,000 2,800,000 2023 $2,926,000 Westgate recognizes revenue over time according to percentage of completion. 8 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts for construction costs incurred).

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please help with attached questions, thanks.

Required Information
[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Complete this question by entering your answers in the tabs below.
View transaction list
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts for construction costs
incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs
incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts for construction costs
incurred).
Journal entry worksheet
<
1 2 3 4
Record construction costs.
Req 2A
Req 2B
In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs
incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
Note: Enter debits before credits.
Req 2C
Date
2021
2021
2822
$2,640,000 $2,300,000
6,160,000 2,660,000
2,080,000 2,860,000
1,840,000 2,800,000
Record entry
General Journal
Clear entry
Debit
2023
$2,926,000
Credit
View general journal
8
5,060,000
5,360,000
>
Transcribed Image Text:Required Information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. View transaction list 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts for construction costs incurred). Journal entry worksheet < 1 2 3 4 Record construction costs. Req 2A Req 2B In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) Note: Enter debits before credits. Req 2C Date 2021 2021 2822 $2,640,000 $2,300,000 6,160,000 2,660,000 2,080,000 2,860,000 1,840,000 2,800,000 Record entry General Journal Clear entry Debit 2023 $2,926,000 Credit View general journal 8 5,060,000 5,360,000 >
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education