In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time. 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2024 2025 2026 Cost incurred during the year $ 2,580,000 $ 3,890,000 $ 3,280,000 Estimated costs to complete as of year-end 5,780,000 3,280,000 0 2. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2024 2025 2026 Cost incurred during the year $ 2,580,000 $ 3,890,000 $ 4,170,000 Estimated costs to complete as of year-end 5,780,000 4,280,000 0
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024 | 2025 | 2026 | |
---|---|---|---|
Cost incurred during the year | $ 1,584,000 | $ 3,240,000 | $ 2,613,600 |
Estimated costs to complete as of year-end | 5,616,000 | 2,376,000 | 0 |
Billings during the year | 1,200,000 | 3,624,000 | 5,176,000 |
Cash collections during the year | 1,000,000 | 2,800,000 | 6,200,000 |
Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.
1. Calculate the amount of revenue and gross
2024 | 2025 | 2026 | |
---|---|---|---|
Cost incurred during the year | $ 2,580,000 | $ 3,890,000 | $ 3,280,000 |
Estimated costs to complete as of year-end | 5,780,000 | 3,280,000 | 0 |
2. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
2024 | 2025 | 2026 | |
---|---|---|---|
Cost incurred during the year | $ 2,580,000 | $ 3,890,000 | $ 4,170,000 |
Estimated costs to complete as of year-end | 5,780,000 | 4,280,000 | 0 |
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images