In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County f $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $ 2,204,000 5,396,000 2,140,000 1,870,000 2025 $ 3,192,000 2,204,000 3,256,000 3,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2026 $ 2,424,400 0 4,604,000 4,930,000

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Please help me with calculation 

Required information
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
2024
2025
$ 2,204,000 $ 3,192,000
5,396,000
2,204,000
2,140,000
3,256,000
1,870,000
3,200,000
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
2024
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.
2025
2026
2026
$ 2,424,400
2024
$ 2,204,000
5,396,000
0
2025
$ 3,870,000
3,170,000
4,604,000
4,930,000
2026
$ 3,270,000
0
Transcribed Image Text:Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2024 2025 $ 2,204,000 $ 3,192,000 5,396,000 2,204,000 2,140,000 3,256,000 1,870,000 3,200,000 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2024 Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. 2025 2026 2026 $ 2,424,400 2024 $ 2,204,000 5,396,000 0 2025 $ 3,870,000 3,170,000 4,604,000 4,930,000 2026 $ 3,270,000 0
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education