In 2023, Sheridan Contractors began construction on an office building. The building was expected to cost $45,510,000 in total and was expected to be completed in early 2025. The customer was to pay Sheridan $48,560,000 for the building. Sheridan was able to use percentage-of-completion accounting for the project, and at the end of 2023 had accumulated $11,377,500 in cost. Sheridan estimated that the costs to complete the construction were in line with the original expected total costs. During 2024, there was a lumber shortage, a strike by construction workers, and various other incidents that dramatically raised costs in the construction industry. As a result, at the end of 2024, Sheridan estimated that the office building would cost an additional $4,990,000 more than originally estimated. To the end of 2024, Sheridan had spent $38,380,000 on constructing the office building. (a1) Your answer is correct. Calculate the revenue to be recognized by Sheridan for the 2024 fiscal year. Revenue to be recognized $ 24765600

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
In 2023, Sheridan Contractors began construction on an office building. The building was expected to cost
$45,510,000 in total and was expected to be completed in early 2025. The customer was to pay Sheridan
$48,560,000 for the building. Sheridan was able to use percentage-of-completion accounting for the project,
and at the end of 2023 had accumulated $11,377,500 in cost. Sheridan estimated that the costs to complete
the construction were in line with the original expected total costs.
During 2024, there was a lumber shortage, a strike by construction workers, and various other incidents that
dramatically raised costs in the construction industry. As a result, at the end of 2024, Sheridan estimated that
the office building would cost an additional $4,990,000 more than originally estimated. To the end of 2024,
Sheridan had spent $38,380,000 on constructing the office building.
(a1)
Your answer is correct.
Calculate the revenue to be recognized by Sheridan for the 2024 fiscal year.
Revenue to be recognized $
24765600
Transcribed Image Text:In 2023, Sheridan Contractors began construction on an office building. The building was expected to cost $45,510,000 in total and was expected to be completed in early 2025. The customer was to pay Sheridan $48,560,000 for the building. Sheridan was able to use percentage-of-completion accounting for the project, and at the end of 2023 had accumulated $11,377,500 in cost. Sheridan estimated that the costs to complete the construction were in line with the original expected total costs. During 2024, there was a lumber shortage, a strike by construction workers, and various other incidents that dramatically raised costs in the construction industry. As a result, at the end of 2024, Sheridan estimated that the office building would cost an additional $4,990,000 more than originally estimated. To the end of 2024, Sheridan had spent $38,380,000 on constructing the office building. (a1) Your answer is correct. Calculate the revenue to be recognized by Sheridan for the 2024 fiscal year. Revenue to be recognized $ 24765600
(a2)
Your answer is partially correct.
Prepare the journal entry to record revenue, construction expenses. (Credit account titles are automatically indented when the
amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts. List
all debit entries before credit entries.)
Account Titles and Explanation
Construction Expenses
Contract Asset/Liability
Revenue from Long-Term Contracts
Debit
38380000
27002500
Credit
24765600
Transcribed Image Text:(a2) Your answer is partially correct. Prepare the journal entry to record revenue, construction expenses. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts. List all debit entries before credit entries.) Account Titles and Explanation Construction Expenses Contract Asset/Liability Revenue from Long-Term Contracts Debit 38380000 27002500 Credit 24765600
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education