Manson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work on a $ 10,500,000 construction contract that was completed in 2021. The following information was taken from Manson’s 2020 accounting records: Billings to date.................................................... $ 3,300,000 Costs incurred..................................................... 3,150,000 Collections to date............................................. 2,100,000 Estimated costs to complete............................ 6,300,000 Under the earnings approach, what amount of gross profit should Manson recognize in 2020 on this contract?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Manson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work on a $10,500,000 construction contract that was completed in 2021. 

The following information was taken from Manson’s 2020 accounting records:

Billings to date

 

$3,300,000

Costs incurred

 

3,150,000

Collections to date

 

2,100,000

Estimated costs to complete

 

6,300,000

What is the amount of revenue that will be recorded in 2020?

In 2020, Pop Construction Corp. began work on a contract for $ 3,700,000. Other details follow:

           2020
Costs incurred during the year.................................................................... $ 1,800,000
Estimated costs to complete as of December 31................................... 1,200,000
Billings during the year................................................................................. 1,650,000
Collections during the year......................................................................... 975,000


Pop uses the percentage-of-completion method. For calendar 2020, Pop should report gross profit of

Mobey Construction Corp. uses the percentage-of-completion method. In 2020, Mobey began work on a contract for $2,475,000 which was completed in 2021. Data on the costs are:

   

Year Ended December 31

   

2020

 

2021

Costs incurred

 

$877,500

 

$630,000

Estimated costs to complete

 

585,000

 

For the calendar years 2020 and 2021, Mobey should recognize gross profit of

Bluegrass Builders Ltd. Is using the percentage-of-completion method for a $ 2,010,000 contract that will take two years to complete. Data at December 31, 2020, the end of the first year, are

Costs incurred to date............................................................ $  925,000
Estimated total costs .............................   2,025,000
Billings to date......................................................................... 850,000
Collections to date..................................................................  700,000


The gross profit or loss that should be recognized for 2020 is

In 2020, Pop Construction Corp. began work on a contract for $3,700,000. Other details follow:

   

            2020

Costs incurred during the year

 

$1,800,000

Estimated costs to complete as of December 31

 

1,200,000

Billings during the year

 

1,650,000

Collections during the year

 

975,000

Pop uses the percentage-of-completion method. For calendar 2020, Pop should report Revenue in 2020 of:

Haven Corp. contracted to construct a building for $ 750,000. Construction began in 2020 and was completed in 2021. Data relating to the contract follow:

Year ended              
           December 31,          
  2020 2021
Costs incurred...................................................................... $ 300,000 $ 230,000
Estimated costs to complete.............................................   200,000


 
Haven uses the percentage-of-completion method. For the calendar years 2020 and 2021, respectively, Haven should report revenue of

Blues Construction Corp. has consistently used the percentage-of-completion method. During 2020, Blues entered into a fixed-price contract to construct an office building for $6,000,000. Information relating to the contract is as follows:

   

         At December 31        

   

          2020

 

          2021

Percentage of completion (to date)

 

15%

 

45%

Estimated total cost at completion

 

$4,500,000

 

$4,800,000

Gross profit recognized (to date)

 

225,000

 

540,000

Under the earnings approach, contract costs incurred during 2021 were

Manson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work on a $ 10,500,000 construction contract that was completed in 2021. The following information was taken from Manson’s 2020 accounting records:

Billings to date.................................................... $ 3,300,000
Costs incurred..................................................... 3,150,000
Collections to date............................................. 2,100,000
Estimated costs to complete............................ 6,300,000


Under the earnings approach, what amount of gross profit should Manson recognize in 2020 on this contract?

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education