ifferent activities that need to be performed to complete a diate predecessor for each activity and the Optimistic, e estimates for each activity. (Times listed are in weeks.) or Optimistic Most Likely 3 32563 6 1 8 5 3 76489 Pessimistic 7 4 15 6 5 9 10 associated with this problem. That is, determine the times and the slack for each activity. Also determine the ect completion time.

A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
icon
Related questions
Question
### Project Management: Activity Duration Analysis

The following table lists seven different activities that need to be performed to complete a project. Also listed are the immediate predecessor for each activity and the Optimistic, Most Likely, and Pessimistic time estimates for each activity. (Times listed are in weeks.)

#### Activity Time Estimates

| Activity | Predecessor | Optimistic (weeks) | Most Likely (weeks) | Pessimistic (weeks) |
|----------|--------------|--------------------|---------------------|---------------------|
| A        | -            | 3                  | 5                   | 7                   |
| B        | -            | 2                  | 3                   | 4                   |
| C        | A            | 5                  | 7                   | 15                  |
| D        | A            | 6                  | 6                   | 6                   |
| E        | C            | 3                  | 4                   | 5                   |
| F        | D            | 1                  | 8                   | 9                   |
| G        | B            | 8                  | 9                   | 10                  |

### Instructions
Sketch and analyze the network associated with this problem. This includes:
1. Determining the earliest and latest start and finish times.
2. Calculating the slack for each activity.
3. Identifying the critical path.
4. Determining the overall project completion time.

### Steps to Analyze the Network
1. **Draw the Network Diagram**: Create nodes for each activity and use directed arrows to represent the precedence relationships.
2. **Calculate Early Start (ES) and Early Finish (EF) Times**:
   - For each activity with no predecessors (start activities), ES = 0.
   - EF = ES + Duration (most likely time).
   - For subsequent activities, ES = Latest EF of preceding activities.
3. **Calculate Late Start (LS) and Late Finish (LF) Times**:
   - Begin with the final activity of the network. LF = Project completion time.
   - LS = LF - Duration.
   - For preceding activities, LF = Earliest LS of succeeding activities.
4. **Calculate Slack Times**:
   - Slack = LS - ES or LF - EF.
   - Slack indicates the flexibility in the schedule of an activity without affecting the overall project completion time.
5. **Determine the Critical Path**:
   - The
Transcribed Image Text:### Project Management: Activity Duration Analysis The following table lists seven different activities that need to be performed to complete a project. Also listed are the immediate predecessor for each activity and the Optimistic, Most Likely, and Pessimistic time estimates for each activity. (Times listed are in weeks.) #### Activity Time Estimates | Activity | Predecessor | Optimistic (weeks) | Most Likely (weeks) | Pessimistic (weeks) | |----------|--------------|--------------------|---------------------|---------------------| | A | - | 3 | 5 | 7 | | B | - | 2 | 3 | 4 | | C | A | 5 | 7 | 15 | | D | A | 6 | 6 | 6 | | E | C | 3 | 4 | 5 | | F | D | 1 | 8 | 9 | | G | B | 8 | 9 | 10 | ### Instructions Sketch and analyze the network associated with this problem. This includes: 1. Determining the earliest and latest start and finish times. 2. Calculating the slack for each activity. 3. Identifying the critical path. 4. Determining the overall project completion time. ### Steps to Analyze the Network 1. **Draw the Network Diagram**: Create nodes for each activity and use directed arrows to represent the precedence relationships. 2. **Calculate Early Start (ES) and Early Finish (EF) Times**: - For each activity with no predecessors (start activities), ES = 0. - EF = ES + Duration (most likely time). - For subsequent activities, ES = Latest EF of preceding activities. 3. **Calculate Late Start (LS) and Late Finish (LF) Times**: - Begin with the final activity of the network. LF = Project completion time. - LS = LF - Duration. - For preceding activities, LF = Earliest LS of succeeding activities. 4. **Calculate Slack Times**: - Slack = LS - ES or LF - EF. - Slack indicates the flexibility in the schedule of an activity without affecting the overall project completion time. 5. **Determine the Critical Path**: - The
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
A First Course in Probability (10th Edition)
A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
A First Course in Probability
A First Course in Probability
Probability
ISBN:
9780321794772
Author:
Sheldon Ross
Publisher:
PEARSON