ifferent activities that need to be performed to complete a diate predecessor for each activity and the Optimistic, e estimates for each activity. (Times listed are in weeks.) or Optimistic Most Likely 3 32563 6 1 8 5 3 76489 Pessimistic 7 4 15 6 5 9 10 associated with this problem. That is, determine the times and the slack for each activity. Also determine the ect completion time.
ifferent activities that need to be performed to complete a diate predecessor for each activity and the Optimistic, e estimates for each activity. (Times listed are in weeks.) or Optimistic Most Likely 3 32563 6 1 8 5 3 76489 Pessimistic 7 4 15 6 5 9 10 associated with this problem. That is, determine the times and the slack for each activity. Also determine the ect completion time.
A First Course in Probability (10th Edition)
10th Edition
ISBN:9780134753119
Author:Sheldon Ross
Publisher:Sheldon Ross
Chapter1: Combinatorial Analysis
Section: Chapter Questions
Problem 1.1P: a. How many different 7-place license plates are possible if the first 2 places are for letters and...
Related questions
Question

Transcribed Image Text:### Project Management: Activity Duration Analysis
The following table lists seven different activities that need to be performed to complete a project. Also listed are the immediate predecessor for each activity and the Optimistic, Most Likely, and Pessimistic time estimates for each activity. (Times listed are in weeks.)
#### Activity Time Estimates
| Activity | Predecessor | Optimistic (weeks) | Most Likely (weeks) | Pessimistic (weeks) |
|----------|--------------|--------------------|---------------------|---------------------|
| A | - | 3 | 5 | 7 |
| B | - | 2 | 3 | 4 |
| C | A | 5 | 7 | 15 |
| D | A | 6 | 6 | 6 |
| E | C | 3 | 4 | 5 |
| F | D | 1 | 8 | 9 |
| G | B | 8 | 9 | 10 |
### Instructions
Sketch and analyze the network associated with this problem. This includes:
1. Determining the earliest and latest start and finish times.
2. Calculating the slack for each activity.
3. Identifying the critical path.
4. Determining the overall project completion time.
### Steps to Analyze the Network
1. **Draw the Network Diagram**: Create nodes for each activity and use directed arrows to represent the precedence relationships.
2. **Calculate Early Start (ES) and Early Finish (EF) Times**:
- For each activity with no predecessors (start activities), ES = 0.
- EF = ES + Duration (most likely time).
- For subsequent activities, ES = Latest EF of preceding activities.
3. **Calculate Late Start (LS) and Late Finish (LF) Times**:
- Begin with the final activity of the network. LF = Project completion time.
- LS = LF - Duration.
- For preceding activities, LF = Earliest LS of succeeding activities.
4. **Calculate Slack Times**:
- Slack = LS - ES or LF - EF.
- Slack indicates the flexibility in the schedule of an activity without affecting the overall project completion time.
5. **Determine the Critical Path**:
- The
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 2 images

Recommended textbooks for you

A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON


A First Course in Probability (10th Edition)
Probability
ISBN:
9780134753119
Author:
Sheldon Ross
Publisher:
PEARSON
